Matter: Nova Scotia Power Inc. (NSPI) - 2024 Load Forecast Report
7 passages 7 documents

Multi Year Planning Cycle across all matters →

N-12024 Load Forecast Report + Appendices - Redacted 1 passage
Section 229
2024 10yr Preliminary Forecast REDACTED (CONFIDENTIAL INFORMATION REMOVED) 2024 Load Forecast Report Appendix E Page 2 of 18 Purpose • As in previous years, this presentation on the preliminary 10-year load forecast provides an opportunity...

AI summary This document outlines the 2024 10-year preliminary load forecast report, including updates from the 2023 forecast, the timeline for preparation and submission, and an agenda for stakeholder engagement.

N-2NSPI (CA) RIR-1 to RIR-9 1 passage
Section 10
2024 Load Forecast Report (NSUARB M11689) NSPI Responses to CA Information Requests NON-CONFIDENTIAL 1 Request IR-3: 2 3 Reference: Board Decision, Matter No. M11307, noting that, “The Consumer Advocate, E1 4 and Eastward Energy supported...

AI summary NSPI responds to an information request about assessing the Hybrid Peak Mitigation electrification profile, noting discussions with the Province of Nova Scotia and the need for a multi-stakeholder study process. The response emphasizes ongoing coordination with the Province and highlights the importance of continuing the Evergreen IRP process ahead of the 2030 deadline.

N-6NSPI (Synapse) RIR-1 to RIR-54 - Redacted 1 passage
Section 33
2025 2026 2027 2028 2029 2030 2031 2032 2033

AI summary A table listing years from 2025 to 2033 with no additional data provided. The structure suggests a multi-year planning framework, but no specific details or context are included in the text.

N-7Evidence of John Wilson, filed on behalf of CA 1 passage
Section 16
Scenario (IRP Action Plan Item 4b). Specifically, it has not established a timeline for 29 participation in a study in partnership with other organizations.18 Considering the long 14 NS Power, 2022 Evergreen IRP Updated Assumptions (Januar...

AI summary The document highlights NS Power's lack of a timeline for participating in a collaborative study, emphasizing the urgency due to long implementation timelines for study recommendations. It references the Integrated Resource Plan (IRP) Action Plan Item 4b and cites multiple regulatory matters.

N-8Evidence of Synapse (BCC) 1 passage
Section 8
2027 2028 2029 2030 2031 2032 2033 2034 Source: Synapse from Figure 1 in NSPI’s 2024 Load Forecast Report (2024 Load Forecast) and responses to Synapse IR-1

AI summary The text presents a series of years (2027–2034) alongside a source citation referencing Synapse’s work in NSPI’s 2024 Load Forecast Report and responses to Synapse IR-1, indicating data related to long-term energy demand projections.

95688Board Decision Letter 1 passage
Section 17
imitations. The CMHC housing completions data is restricted to population centres of 10,000+, whereas population centres below 10,000 are estimated on a sample basis in the last month of each quarter. The Board acknowledges the intervenors...

AI summary The Board acknowledges intervenors' input on the Load Forecast and directs NS Power to improve forecasting by engaging stakeholders, reassessing variables, and updating studies. NS Power must address unexplained residential sector variance in the 2025 report.

95688Board Decision Letter 1 passage
Section 17
imitations. The CMHC housing completions data is restricted to population centres of 10,000+, whereas population centres below 10,000 are estimated on a sample basis in the last month of each quarter. The Board acknowledges the intervenors...

AI summary The Board acknowledges intervenor input on the Load Forecast and directs NS Power to improve stakeholder engagement, reassess modeling variables, update studies, and investigate unexplained residential NSR variance in the 2025 Load Forecast Report.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →