N-1Work Order - Redacted 1 passage
7.0 ALTERNATIVE ANALYSIS p. pp. 40-41
7.0 ALTERNATIVE ANALYSIS This section compares the alternatives described in Section 6 using preliminary capital cost estimates, economic analysis, and qualitative planning considerations. Where applicable, the alternatives are compared us...

AI summary The section compares alternatives using capital cost estimates, economic analysis, and qualitative planning considerations, employing the NS Power economic model and NPV results to inform the final recommendation.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →