e of third- 27 order combination of wind, solar and storage diversity benefit, the benefit is not anticipated 28 to have an impact on capacity additions to meet our 2030 targets. 1 Pages 36 – 38 of 89, Diversity Benefit ELCC Values, Pre-IR...
AI summary NSPI's 2023 10-Year System Outlook Report response to NSUARB's IR-10 request highlights delays in the Reliability Tie project (second 345 kV circuit between Nova Scotia and New Brunswick). The Board's 2016 letter noted only 86% progress by 2015, with no advancement since 2013/2014. NSPI claimed 'more substantial progress' was expected in 2016 but provided no explanation for the delay.