N-1Application - Redacted
5 passages
.................................... 23 17 6.1.5 Commercial Net Metering ........................................................................ 25 18 6.1.6 Additional Renewable Energy Procurements ...........................................
AI summary The document outlines sections of an Integrated Resource Plan (IRP) action plan, including commercial net metering, battery storage projects, renewable energy integration, the NS-NB Reliability Intertie Project, fast-acting generation, fuel conversions, and coal phase-out initiatives. Key topics include renewable energy procurement, grid stability, and infrastructure planning.
1 6.2.3 Grid Stability & Renewable Integration Resources 2 3 Transitioning from a traditional power system which is largely made up of synchronous generators 4 to a power system which will rely heavily on inverter-based resources (IBRs) su...
AI summary Transitioning to inverter-based resources (IBRs) like wind and solar requires grid stability measures such as synchronous condensers and FACTS devices. NS Power, following DOE directives, prioritizes inertial support projects at Benjamin’s Mill and Wedgeport. The NS-NB Reliability Intertie Project aims to enhance transmission reliability between Nova Scotia and New Brunswick.
1 Incorporated (WTI) was formed in Nova Scotia as an ownership arrangement pursuant to the 2 Prescribed Projects Regulations made under the NS Public Utilities Act, to facilitate a low-cost 3 equity investment in the Project by the Canada...
AI summary WTI, a deemed utility under the Public Utilities Act, submitted an application for project cost approval and rate base establishment for the NS-NB Reliability Intertie Project. The NSEB approved the project in November 2025, directing WTI to update progress on the Path to 2030 timeline and participate in NS Power’s ACE Plan proceedings. Land acquisition and right-of-way clearing in Nova Scotia and New Brunswick are progressing ahead of schedule.
of the Nova Scotia ROW is complete ahead of schedule and work is 21 advancing to clear the final NS ROW segment near the NS/NB border. 22 23 NS Power received approval for the Environmental Assessment of the Nova Scotia portion of the 24 R...
AI summary The Nova Scotia portion of the NS-NB Reliability Intertie Project is progressing ahead of schedule, with final ROW clearing near the NS/NB border. NS Power received EA approval in December 2023, while NB Power submitted its EIA in late 2024, expecting approval in December 2025. Major vendors have been selected for transmission line materials and construction.
1 9.0 CONCLUSION 2 3 The Nova Scotia 2030 Clean Power Plan and The Path to 2030 represent a comprehensive clean 4 energy transition plan that is aligned with NS Power’s most recent IRP Action and Roadmap 5 update. Delivering on this plan w...
AI summary The Nova Scotia 2030 Clean Power Plan and The Path to 2030 outline a clean energy transition aligned with NS Power’s Integrated Resource Plan (IRP). Key 2025 progress includes wind farm construction, Power Purchase Agreements (PPAs) for 262 MW of wind capacity, Battery Energy Storage System (BESS) developments, NSEB approval for the Reliability Intertie project, and community solar initiatives.