3.3. Progress Updates on Roadmap Items for 2024/2025 to Date
p. p. 8
3.3. Progress Updates on Roadmap Items for 2024/2025 to Date - Existing thermal unit cost updates: NSPI has updated cost profiles for sustaining capital investment for its existing thermal units. These will be incorporated in future IRP mo...
AI summary NSPI has updated thermal unit costs for future IRP modeling, engaged with hydrogen developers, assessed geothermal potential, and monitored SMR policy changes. Hydrogen blending data and SMR legislation did not trigger IRP updates, while geothermal requires more data and is unlikely to be commercialized before 2030.