Topic:"Operating Expenses" in M03508

Matter: CI# 38857 - P-128.10 - NSPI WO - L7004 Deteriorated Replacements - $2,467,028
1 passage 1 document

Operating Expenses across all matters →

N-2Redacted Responses to Information Requests 1 passage
1 Rows Processed p. p. 0
1 Rows Processed 1 Request IR-3: 18 (a) "NSPI's contractor management model takes the following into consideration: 19 20 • The nature of the work to be undertaken (e.g. transmission versus distribution, 21 live line versus deadline, custo...

AI summary NSPI's contractor management model considers factors such as the nature of work, workforce availability, project scope, and location. Reasons for engaging contractors include intermittent work requirements, lower costs, varying work locations, and the need for specialized skills.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →