Success will be measured by: p. p. 15
Success will be measured by: - 1. Completion of low NOx retrofits on Lingan Unit 1, Point Tupper Unit 2, and Trenton Unit 6 in accordance with established safety performance targets and within schedule and budget; and - 2. Performance demo...

AI summary Success is defined by completing low NOx retrofits on three specific power units within safety, schedule, and budget targets, and by confirming performance guarantees through testing. These criteria ensure compliance with regulatory and operational standards.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →