E-17Savings Verification Report - BCC H. Gil Peach 3 passages
Operation p. p. 68
Operation SEM is delivered through a third-party Service Provider under E1 oversight. The participation journey typically includes: an eligibility check and memorandum of understanding; a kick-off meeting; data collection and the developme...

AI summary The Strategic Energy Management (SEM) program is delivered by a third-party service provider under E1 oversight. It involves various steps like eligibility checks, data collection, and energy improvement events. Participants receive performance-based incentives, with different rates for standard and large industrial participants.

Conclusion p. p. 76
Conclusion Custom Incentives performed the strongest of 2025 BNI programs, exceeding both energy and demand targets and producing realization rates above 100% for Custom services. The five sub-programs - Retrofit, P4P, New Construction, BO...

AI summary Custom Incentives exceeded energy and demand targets in 2025 BNI programs, with realization rates above 100%. The five sub-programs cover a wide range of customer needs. Compressed air leak surveys are highlighted as a cost-effective measure, contributing significantly to program savings. Evaluation methods are largely consistent with industry practice, except for compressed air measurement.

Key Findings p. p. 79
Key Findings - SBES did not meet its net energy or peak demand savings targets, falling short by 38% and 46% respectively — the largest gap to plan among the four 2025 BNI / small-business program elements. - Total participation (units reb...

AI summary SBES did not meet its energy and peak demand savings targets, missing by 38% and 46% respectively. Participation in the DIY pathway was dominant, with minimal impact from updated lighting parameters on overall savings. E1's tracking process was confirmed as accurate, with shortfalls due to low participation rather than measurement errors.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →