Section 43
eduled outages, Lingan Unit 2 will be available, if needed, 18 to provide firm capacity and maintain an adequate planning reserve margin (Section 6.2) for the 19 upcoming winter (2023/2024). 20 DATE FILED: June 30, 2023 Page 17 of 59 2023...

AI summary The document discusses the availability of Lingan Unit 2 for providing firm capacity and maintaining an adequate planning reserve margin during the upcoming winter (2023/2024). It references the 2023 10-Year System Outlook, filed on June 30, 2023.

Section 99
Page 41 of 59 2023 10-Year System Outlook NON-CONFIDENTIAL 1 The Ten-Minute Reserve Responsibility for NS Power is typically 32 MW 41 of spinning reserve 2 on the system. Additional regulating reserve is maintained to manage the variabilit...

AI summary The document outlines the Ten-Minute Reserve Responsibility for NS Power, which is 32 MW of spinning reserve. It also discusses the Planning Reserve Margin (PRM) and the NPCC reliability criteria approved by the NSUARB, emphasizing the need to ensure resource adequacy and maintain reliability in the bulk power system.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →