2. What Considerations and contingencies will be available to NS Power to ensure construction completion in November given the potential impacts from COVID-19?
p. p. 33
2. What Considerations and contingencies will be available to NS Power to ensure construction completion in November given the potential impacts from COVID-19? NS Power has provided a revised construction schedule in Section 2.2. NS Power...
AI summary NS Power has requested a delayed construction start and completion date for a project due to considerations such as upstream alewife migration, fish spawning windows, and potential impacts from COVID-19. They have implemented safety protocols and successfully managed projects under pandemic restrictions in 2020.