N-22Responses to Undertakings 1-22
3 passages
FOR PETROLEUM IMPACTED SITES IN ATLANTIC CANADA Pha III E SA Rep ort, Se ctio n 5 .4 se 12 13 T011 – Provincial Planned Transmission Line was underspent due to outage availability impacting 14 the ability of planned work to take place as w...
AI summary The text discusses issues related to the Provincial Planned Transmission Line (T011) being underspent due to outages and engineering delays. It also references a correction in the 2026 ACE Plan Application regarding the 2024 ACE Plan budget and actuals. Additionally, it addresses a request to review outage events and condition ratings for specific feeders listed in an application.
2026 ACE Plan U-18 Attachment 1 Page 2 of 2 1 Undertaking U-19: % Total Customer Hours of Interrupts (CHI) Adverse Environment 0.6% 0.4% 0.2% 0.3% 0.1% 7.6% 0.5% 0.0% 1 ( / Adverse Weather 36.3% 57.3% 23.7% 23.6% 47.3% 29.8% 14.6% 10.6% De...
AI summary This table presents the distribution of customer interruptions and events across various causes for the 2026 ACE Plan. It includes percentages for factors such as adverse weather, defective equipment, tree contacts, and loss of supply, providing insights into the primary causes of service interruptions.
2026 ACE Plan U-20 Attachment 1 Page 1 of 1 1 00 11 Scheduled Outage 29,579 50,696 36,753 37,049 39,790 74,258 105,051 152,555 Tree Contacts 247,746 276,518 157,884 159,800 466,022 375,838 165,741 241,373 Unknown 69 970 43 321 34 065 33 44...
AI summary The document discusses an undertaking related to vegetation management work on 23 feeders in 2024, providing an updated response to NSEB IR-132. It explains that specific costs per distribution feeder have not been fully recovered due to the 2025 cyber incident and refers to Attachment 1 for estimated costs based on the average cost per kilometer in 2024.
20260421-1Hearing Transcript — 04/21/2026 (Revised Transcript - Refiled May 20, 2026)
7 passages
NS POWER PANEL 99 Cr-ex, (Murphy) outages that were coded as a cause due to a tree. Q. Caused due to a tree, but it includes adverse weather. I guess A. (MacMullin) Yeah, I hear you. Q. Yeah. A. (MacMullin) So there's the way we look at ou...
AI summary The discussion revolves around outage coding practices, specifically how outages caused by trees are distinguished from those caused by adverse weather. The witness explains that outages are categorized based on cause codes, and while some are due to tree contact, others may be due to weather or other factors, and these are tracked separately.
NS POWER PANEL 103 Cr-ex, (Murphy) 1 our system to be understanding that a certain portion of 2 those, conservatively 40 percent of adverse weather coded 3 outages, are in fact due to trees. 4 I guess just to go back, though, Q. 5 is it po...
AI summary The discussion centers on the classification of power outages caused by tree contacts during adverse weather. It clarifies that tree contacts are only coded when the crew visually confirms the presence of a tree on the line during an outage, even if the tree was previously leaning on the line and no longer is when the crew arrives.
1 that's correct. Forty (40) percent of outages that would 2 have been coded as adverse weather would have been 3 subsequently updated to be shown to be reflecting a tree 4 contact cost code. 5 Q. So the adverse weather line would 6 be wit...
AI summary The discussion addresses the reclassification of outage causes, specifically moving 40% of adverse weather outages to tree contact causes. It also covers Nova Scotia Power's evaluation of a pooling arrangement for spare transformers, with the last assessment conducted in 2024.
- break, probably. 1 Regardless, Mr. Pickles, as it relates 11 it evaluates the conditions and the criticality of its 12 assets to evaluate and make recommendations in the Five 13 Year Reliability Plan. That's correct? 14 A. (MacMullin) Th...
AI summary The text discusses the evaluation of asset conditions and criticality in the context of the Five-Year Reliability Plan, with confirmation that the plan was reviewed within this context rather than through a standalone review.
NS POWER PANEL 299 Cr-ex, (Mahody) 1 looking at a feeder level, when you start looking at a 2 system level, there's so many puts and takes that that's 3 when we say things like that they can mask the input, that 4 to do a straight sum does...
AI summary The discussion addresses challenges in assessing the impact of asset replacement on system reliability. While Nova Scotia Power aims to measure improvements in asset performance, the complexity of system-level interactions makes it difficult to provide a single metric for reliability improvements.
NS POWER PANEL 319 Cr-ex, (Mahody) 1 this project. And the question I wanted to focus in on is 2 BY MR. MAHODY: 3 Witness panel, I'm headed to the Q. 4 Pennsylvania breaker issue. 5 If we could call up N-1, page 402, 6 please. 7 And so you...
AI summary The text references a regulatory proceeding involving Nova Scotia Power, focusing on the Pennsylvania breaker issue and the determination of risk levels associated with circuit breakers. It includes references to specific pages and Board IR-126.
NS POWER PANEL 353 Cr-ex, (Mahody) 1 units. 2 In terms of the specific criteria that 3 were used to select these, I wouldn't have the specifics, 4 but I could say that it does definitely include looking at 5 the ability to reduce that outa...
AI summary The discussion revolves around the selection criteria for outage response improvements and the need to update a capital spending forecast figure for 2025. The importance of RTU functionality in reducing response times and the need for updated financial data are highlighted.
20260422-1Hearing Transcript — 04/22/2026 (Revised Transcript - Refiled May 20, 2026)
10 passages
1 that's included in the project cost amount right now, does 2 that incorporate a contingency for the feedback that you 3 have received from Department of Fisheries and Department 4 of Transport Canada? 5 A. (Drover) Yes, it does. 6 Q. The...
AI summary The discussion revolves around project scheduling and contingency planning for the Tufts Cove 3 project, including considerations for work during a planned outage and potential impacts on the outage timeline.
NS POWER PANEL 391 Questions, (Murphy) I don't know, for delay in this particular project. So if the outage was to start on October 2nd and this project didn't start on October 2nd and perhaps got delayed a little bit, then that could pres...
AI summary The discussion addresses concerns about potential delays in a shoreline refurbishment project and their impact on an outage schedule. Concerns are raised about the possibility of additional costs to ratepayers if the project causes the outage to extend beyond the proposed window, particularly if the contract lacks provisions for liquidated damages.
NS POWER PANEL 437 Questions, (Murphy) 1 So as a part of this capital 12 13 14 15 16 Please provide the number of outage events, by year, for each feeder listed in attachment 1. MEMBER MURPHY: And if you scroll 17 down, Rob? 18 BY MEMBER M...
AI summary The document outlines a regulatory proceeding involving NS Power, where specific questions are raised regarding outage events and condition ratings for feeders listed in Attachment 1, as well as the review of an IR response to a revised IR-19. The discussion centers on compliance and accuracy of data provided.
1 average duration, there's not really an improvement from 2 2021 to 2024 and there was $57 million spent. 3 A. (MacMullin) So it is absolutely 4 the intent of the investment program, the $45 million last 5 year and the $45 million this ye...
AI summary The discussion highlights NS Power's investment in vegetation management to reduce outage duration and frequency, with a 19% reduction in tree-related outages from 2024 to 2025. The focus is on prioritizing high-risk feeders, and the speaker requests detailed data on customer interruptions and hours of interruption for lines where vegetation management was performed from 2020 to 2025.
relates to those figures, that the numbers in those figures exclude any impacts from MEDs and the EEDs. A. (MacMullin) That's correct. Q. Thank you. MEMBER MURPHY: Rob, can you call up Exhibit N-7, PDF page 30? That's the response to the S...
AI summary The discussion addresses discrepancies between figures showing customer interruptions in 2022, with one figure showing 714,000 and another 810,000. The difference is explained by the exclusion of planned outages and significant events in the performance standards figure, which is used for regulatory reporting.
NS POWER PANEL 465 Questions, (Murphy) 1 or the figure in your in the I believe the response 2 to the CA, that is just major and extreme events. So I 3 would expect the Figure 3 to have a lower value in some 4 cases due to the planned outa...
AI summary Member Murphy questions the discrepancy in figures related to planned outages and customer hours of interruption, noting an increasing trend in spending and interruptions despite previous decreasing trends. The response highlights the importance of context, particularly events in 2022 and 2023, in understanding the figures.
NS POWER PANEL 469 Questions, (Murphy) 1 doing are showing benefits. We are seeing we 2 absolutely are seeing a reduction in the duration and 3 frequency of outages due to trees. It has it is 4 evidenced in the data and in the evidence tha...
AI summary The text discusses improvements in the Vegetation Management Program, noting a reduction in outage duration and frequency due to tree-related issues. It also mentions changes in how the program is presented, adapting to higher wind exposure and involving customers in tree management.
NS POWER PANEL 475 Questions, (Murphy) 1 MEMBER MURPHY: Rob, can you to N-1, 8 compared to 2023. But based on the updated figure, would 9 you agree with me that the reduction is only really 6 10 percent now? 11 (MacMullin) It's correct. Th...
AI summary Member Murphy questions Rob about the reduction in N-1 compared to 2023 and notes that the reduction is only 6 percent. Rob confirms the initial numbers were year-to-date end of October, and the reduction was lessened by year-end. Murphy also points out that 2025 numbers are similar to 2021 and worse than 2020. Rob agrees and reiterates the goal of the Five-Year Reliability Plan to reduce outage durations and meet performance standards by 2029.
1 finish your questions and move on with Mr. Wilson, if 2 that's okay with everyone. 3 THE CHAIR: So break now and then 4 yeah, let's do that. Let's do that. 5 So let's come back at 1:30. 6 Upon recessing at 12:21 p.m. 7 Upon resuming at 1...
AI summary The proceeding involves a discussion about the D055 Planned Replacement of Deteriorated Equipment Routine, with a focus on a discrepancy between projected and actual spending, leading to a $15 million adjustment. The Chair is asking questions regarding this adjustment and its implications.
NS POWER PANEL 517 Questions, (Chair) 1 Q. If we can is there sort of a 2 reflexivity between D005, which is the planned, and the 3 D055 which is planned and D005, which is the unplanned? 4 Is there reflexivity between the two? In other wo...
AI summary The discussion focuses on the relationship between planned (D005) and unplanned outages, noting that increasing planned replacements could reduce unplanned ones over time. It also highlights potential increased operational costs from reactive responses to unplanned outages, such as overtime labor.