N-4Responses to Third Set of Information Requests 8/30/2010 1 passage
NON-CONFIDENTIAL p. p. 0
NON-CONFIDENTIAL 1 Response IR-11: (cont'd) 2 3  February 20 – June 16: Generating 4  June 16: Blowout occurred in the upper section of the woodstave pipe and it was 5 dewatered. The pipe remained out of service to Dec. 31. 6  June 24-2...

AI summary The document outlines the timeline and actions taken by NSPI regarding the repair of a damaged woodstave pipe, including inspection, assessment, application filing, and project execution as part of the ACE 2010 plan.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →