DESCRIPTION: This project includes the installation and protection of a replacement submarine cable from Brownsville to Big Island, Pictou County. The existing single-phase primary submarine power cable is approximately 1,400m long. It has...
AI summary This project involves replacing a 1,400m single-phase primary submarine power cable between Brownsville and Big Island, Pictou County, due to the cable reaching the end of its service life. The replacement aims to ensure reliable service to customers.
Why do this project ? The existing submarine power cable was installed in 1977, and is the only source of power for customers on Big Island. The cable has reached the end of its design life and an unplanned failure of the cable, and the su...
AI summary The existing 1977 submarine power cable serving Big Island has reached the end of its design life, posing a risk of extended outages if it fails. Installing a new cable while the existing one remains operational will enhance service reliability and availability for customers.
Title: 539N-201 Big Island Subsea Cable Replacement Description Unit Quantity Un it Estimate To tal Estimate Cost Support Reference Completed Simi Projects (FP#'s Regular I abour Engineering PD 318 $ 452 143,881 Sub-Total $ 143,881 Mater i...
AI summary The document outlines the cost estimates for the Big Island Subsea Cable Replacement project, detailing various components such as engineering, materials, and installation costs. The table provides a breakdown of costs for different phases of the project, including cable installation, surveying, and site supervision.