4.2 Current mandate under Phase 1 p. pp. 9-10
4.2 Current mandate under Phase 1 Under Phase 1, which is currently in effect, IESO Nova Scotia is responsible for system planning, energy resource procurement, and interconnection functions. Responsibility for system operation and dispatc...

AI summary Under Phase 1, IESO Nova Scotia manages system planning, energy procurement, and interconnection, while NS Power retains system operation and OATT ownership. These responsibilities will transfer to IESO Nova Scotia under Phase 2 once the MAEA is proclaimed, though some provisions remain unproclaimed.

103397SBA (IESO Nova Scotia) IR 1 to 12 1 passage
Request IR-3:
Request IR-3: Refer to M13007, Exhibit N-1, Application, Section 3.3 Allocation of Revenue Requirement to Market Participants, page 16 of 48, at lines 7-22. a) What changes does the transition to Phase 2 entail in terms of employee assignm...

AI summary Request IR-3 and IR-4 seek clarification on changes in employee assignments during Phase 2, the functions performed by IESO-NS under the Open Access Transmission Tariff, and the relevance of jurisdictional scan findings to Nova Scotia. They also ask about the entities served by IESO-NS, the applicability of the More Access to Energy Act, and financial assurance requirements for market participants.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →