Topic/Matter Intersection

Topic:"Power Infrastructure" in M13173

Matter: Nova Scotia Independent Energy System Operator (IESO Nova Scotia) - 2027/2028 Proposed Expenses, Revenue Requirement and Fees Application
2 passages 1 document

Power Infrastructure across all matters →

N-1Application - Redacted 2 passages
11 Control Center Build p. p. 125
11 Control Center Build 12 Control Centre Build includes the design, construction, fit-out, physical security systems, and 13 commissioning of t he IESO Nova Scotia Control Centre at the Atlantic Data Centre. This includes 14 t he dedicate...

AI summary The Control Centre Build involves the design, construction, and commissioning of the IESO Nova Scotia Control Centre at the Atlantic Data Centre. This facility is a foundational component for the transition to an independent system operator under the More Access to Energy Act (MAEA). It enables IESO Nova Scotia to independently manage real-time operations of Nova Scotia's bulk electricity system and assume Balancing Authority (BA) and Transmission Operator (TOP) responsibilities, independent of Nova Scotia Power.

3. Control Center Build: p. p. 199
3. Control Center Build: - Description: Covers the design, construction, fit-out, physical security systems, and commissioning of the IESO-NS control center. This includes the dedicated primary control centre facility and operating workfor...

AI summary The text describes the scope and basis for the IESO-NS control center build. This project encompasses the design, construction, fit-out, physical security, and commissioning of a dedicated facility. The primary objective is to provide the IESO-NS with an environment and workforce capable of conducting real-time operational control independently of Nova Scotia Power (NSP). The cost estimates for this project are derived from professional judgment and benchmarks from analogous control center projects and historical data.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →