ONE PART DISTRIBUTION VOLTAGE REAL TIME PRICING TARIFF Page 2 of 3 p. p. 37
ONE PART DISTRIBUTION VOLTAGE REAL TIME PRICING TARIFF Page 2 of 3 - o By midnight each business day, hourly price forecasts for each hour of the next five days shall be provided to the customer. - o Major changes to the hourly price forec...

AI summary This section outlines the operational requirements and conditions for the Voltage Real Time Pricing Tariff. Key provisions include the requirement for the Company to provide hourly price forecasts for the next five days, rules for primary vs. secondary metering and associated capital contributions, and a minimum twelve-month service term. It also specifies conditions for transitioning from an Interruptible Rider to firm service and establishes a minimum power factor requirement of 90% lagging to avoid adjustment factors.

SPECIAL CONDITIONS p. p. 37
SPECIAL CONDITIONS - (1) The Port Authority owns and is responsible for the maintenance and operation of all electrical equipment required for the supply of port electricity to docked ships other than the meters and metering transformers s...

AI summary This section outlines the special conditions for port electricity supply, defining the division of responsibilities between the Port Authority and Nova Scotia Power Inc. (NSPI). It specifies that the Port Authority maintains most electrical equipment while NSPI manages meters. Key requirements include the Port Authority providing trained staff for ship connections, submitting a two-year vessel demand schedule, and providing capital contributions for primary metering or special communication systems. It also establishes technical standards for metering, transformer loss adjustments, and minimum power factor requirements.

Preamble p. p. 37
- (9) The customer will make all necessary arrangements and bear all costs of ensuring that its load does not unduly deteriorate the integrity of the power supply system, by reason of its design and/or operation. These specific requirement...

AI summary The text outlines the responsibilities of customers regarding the integrity of the power supply system. Customers are required to arrange for and bear all costs associated with ensuring their load does not adversely affect the system's design or operation. These requirements must be formalized in a written operating agreement. The text further specifies that the assessment of system integrity impacts will include factors such as reliability, harmonic levels, voltage flicker, unbalance, load rate of change, stability, and fault levels.

SPECIAL CONDITIONS p. p. 37
SPECIAL CONDITIONS - (1) NS Power reserves the right to have a separate service agreement, if in the opinion of NS Power issues not specifically set out herein, must be addressed for the ongoing benefit of NS Power and its customers. - (2)...

AI summary This section outlines special conditions for the Standby Service Tariff. It establishes Nova Scotia Power's right to enter separate service agreements, mandates that Licensed Retail Suppliers (LRS) ensure their generation and load do not compromise power supply system integrity, and defines technical parameters for assessing system integrity (e.g., reliability, harmonics, and voltage). It also specifies that the LRS must prove a resource is dispatchable to receive a non-zero capacity contribution factor in billing demand calculations.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →