NON-CONFIDENTIAL 1 Response IR-11: (cont'd) 2 3 February 20 – June 16: Generating 4 June 16: Blowout occurred in the upper section of the woodstave pipe and it was 5 dewatered. The pipe remained out of service to Dec. 31. 6 June 24-2...
AI summary The document outlines the timeline and actions taken by NSPI regarding the repair of a damaged woodstave pipe, including inspection, assessment, application filing, and project execution as part of the ACE 2010 plan.