Topic:"Procurement Practices" in M03413

Matter: CI# 39323; CI# 39626; CI# 39627; & CI# 39628 - P-128.10 - NSPI WO - (Digby Wind Project) Application for approval of capital work orders  in the amount of $82.8 million for the acquisition, construction and interconnection of the Digby Wind Farm Project
61 passages 7 documents

Procurement Practices across all matters →

N-1Application 15 passages
1 6.0 EQUIPMENT AND SERVICES SELECTION 2 3 The contract for the 20 General Electric 1.5sle wind turbines was originally executed by 4 Skypower effective March 2009, before the involvement of NSPI or 324 NSL. Each turbine has 5 the following characteristics: 6 7 1.5 MW rated capacity units 8 A hub height of 80 metres 9 Rotor diameter of 77 metres 10 Manufactured in the United States and Canada 11 2 year warranty 12 13 The Company has negotiated an Operating and Maintenance (O&M) Services Agreement with 14 General Electric (GE) to provide Original Equipment Manufacturer (OEM) ongoing technical 15 expertise and access to GE's spare parts inventory. 16 17 When 324 NSL purchased the Project assets, a significant turbine deposit had been paid to GE 18 by Skypower. 324 NSL secured the turbine contract net of this deposit. NSPI has selected 19 different turbines at other sites (for example, Enercon turbines are being used at Nuttby 20 Mountain). Careful consideration was given to the use of the GE 1.5sle turbines for this Project 21 in light of NSPI's review and experience with other project sites. In light of all the 22 circumstances involved, including the value inherent in the pre-existing turbine deposit, the GE 23 1.5sle turbine continues to represent the appropriate turbine option for this Project. p. p. 17
1 6.0 EQUIPMENT AND SERVICES SELECTION 2 3 The contract for the 20 General Electric 1.5sle wind turbines was originally executed by 4 Skypower effective March 2009, before the involvement of NSPI or 324 NSL. Each turbine has 5 the followin...

AI summary The document details the selection of General Electric 1.5sle wind turbines for a project, originally contracted by Skypower in 2009. NSPI and 324 NSL later acquired the project, retaining the GE turbines due to a pre-existing deposit and operational considerations. An O&M agreement with GE ensures technical support, while other NSPI sites use different turbine models.

14. INTELLECTUAL PROPERTY p. p. 17
14. INTELLECTUAL PROPERTY - 14.1 All Intellectual Property that arises in the course of the Project shall vest in the Proponent. - 14.2 The Proponent shall supply to Canada the reports and documents described in Schedule B or as otherwise...

AI summary The Proponent retains all intellectual property from the Project, granting Canada a non-exclusive, royalty-free license to use and modify reports for non-commercial governmental purposes.

Why do this project this way? p. p. 17
Why do this project this way? The line is being built using single pole construction to minimize cost and right of way reqUirements. The routing was established through extensive landholder negotiation to provide the optimal route with min...

AI summary The transmission line uses single-pole construction to reduce costs and right-of-way requirements, with routing determined via landholder negotiations. Labour is sourced through NSPl's existing Power Line Technician Service Agreement with EUS, aligning with NSPl's force planning model for resource optimization.

MATERIAL CONTRACTS p. p. 62
MATERIAL CONTRACTS - 1. the Leases; - 2. the Options; - 3. the Eco Energy Agreement; - 4. the EUS Agreement; - 5. the GE Contract; - 6. the Generator Interconnection Agreement; - 7. the Magna Purchase Order; - 8. the Services Agreement; an...

AI summary The document lists key material contracts and agreements, including leases, options, the EcoEnergy Agreement, EUS Agreement, GE Contract, and others, which are central to the regulatory proceeding.

BETWEEN: p. p. 62
BETWEEN: 3240384 NOVA SCOTIA LIMITED a body corporate, incorporated under the laws of Nova Scotia (the "Vendor") - and- NOVA SCOTIA POWER INCORPORATED, a body corporate, incorporated under the laws of the Province of Nova Scotia (the "Purc...

AI summary A legal agreement between 3240384 NOVA SCOTIA LIMITED (Vendor) and NOVA SCOTIA POWER INCORPORATED (Purchaser) outlines the sale of assets under a May 28, 2010 Purchase Agreement. The parties acknowledge mutual consideration and agree to the terms described in Schedule 'A' of the Purchase Agreement.

A. Assets Acquired by 3240384 Nova Scotia Limited since December 23, 2009: p. p. 62
A. Assets Acquired by 3240384 Nova Scotia Limited since December 23, 2009: Procurement and Construction Contract Emera Utility Services Inc. 3240384 Nova Scotia Limited February 9, 2010 Standard Generator Interconnection and Operating Agre...

AI summary This section lists various procurement and construction contracts, agreements, and studies related to assets acquired by 3240384 Nova Scotia Limited since December 23, 2009. These include interconnection agreements, environmental studies, and contracts with multiple entities.

A. Assets Acquired by 3240384 Nova Scotia Limited since December 23, 2009: p. p. 62
Procurement and Construction Contract Emera Utility Services Inc. 3240384 Nova Scotia Limited February 9, 2010

AI summary The document lists a procurement and construction contract between Emera Utility Services Inc. and 3240384 Nova Scotia Limited, dated February 9, 2010.

1. Turbine Supplier (General Electric) Documents p. p. 30
1. Turbine Supplier (General Electric) Documents - Turbine Supply Agreement and Exhibits (attached) - General Electric 1.5 MW SLE (Non-ESS) Wind Turbine Technical Documents (attached) - SCADA Documentation (attached)

AI summary The section lists documents submitted by General Electric (GE) related to turbine supply agreements, technical specifications for wind turbines, and SCADA systems. These materials are part of the regulatory proceeding involving turbine supplier documentation.

1.2 Design Documentation p. p. 30
1.2 Design Documentation Constmction Schedule Design Criteria Specification Geotechnical Investigations Site Surveys BOP Equipment Specification BOP Contract Specifications Bid review and recommendation documents Drawing List Electrical Sc...

AI summary The section outlines design documentation requirements, including technical specifications, construction schedules, geotechnical investigations, vendor contracts, and operational manuals for a project.

1.3 Construction Phase Documentation p. p. 30
1.3 Construction Phase Documentation Meeting Minutes Progress Reports Turnover PaCkages Constmction Photographs Safety Plan Safety Meeting Minutes Site Safety Records Work Estimate Fonn Contemplated Change Order Form Change Order Fonn Site...

AI summary The section outlines construction phase documentation requirements, including meeting minutes, safety records, work estimates, change order forms, and site instructions, emphasizing project management and compliance during infrastructure development.

2.5.00 Notes: p. p. 30
2.5.00 Notes: Design includes engineering, calculations, drawings, specifications. Procurement includes tender preparation, evaluating bids with input of DEVELOPER, pre-award meetings and negotiations, and evaluations / recommendations. Co...

AI summary The text outlines three phases of a project: design (engineering, calculations, specifications), procurement (bid evaluation with developer input, pre-award meetings), and construction management (ensuring contractors meet safety, environmental, schedule, cost, and quality requirements).

EXCLUSIONS TO SCOPE OF WORK p. p. 85
EXCLUSIONS TO SCOPE OF WORK - Turbine procurement and transportation. The CONTRACTOR is responsible for offloading at the laydown area on the Site (Digby Wind Farm). - Main transfOlmer procurement (Contractor will transport the main transf...

AI summary The scope of work excludes turbine procurement, transportation, environmental permits, building permits, land leases, and easements at the Digby Wind Farm site. The CONTRACTOR is responsible for offloading turbines at the laydown area and transporting the main transformer from temporary storage.

5.1.1 Standard Option p. p. 85
5.1.1 Standard Option The Transmission Provider shall design, procure, and construct the Transmission Provider's Interconnection Facilities and Network Upgrades, using Reasonable Efforts to complete the Transmission Provider's Interconnect...

AI summary The Transmission Provider must design, procure, and construct interconnection facilities and network upgrades by specified deadlines in Appendix B, using reasonable efforts and adhering to safety practices, labor agreements, and regulations. If delays occur, written notice must be provided, and efforts to meet revised deadlines are required.

5.5 Equipment Procurement p. p. 85
5.5 Equipment Procurement If responsibility for construction of the Transmission Provider's Interconnection Facilities or Network Upgrades is to be borne by the Transmission Provider, then the Transmission Provider shall commence design of...

AI summary The Transmission Provider must design and procure equipment for Interconnection Facilities or Network Upgrades once three conditions are met: completing the Facilities Study, receiving written authorization from the Interconnection Customer by a specified date, and providing required security as outlined in Article 11.5. These obligations are subject to written agreement between the Parties.

5.7 Work Progress p. p. 85
5.7 Work Progress The Parties will keep each other advised periodically as to the progress of their respective design, procurement and construction efforts. Either Party may, at any time, request a progress report from the other Party. If,...

AI summary The Parties agree to provide periodic updates on design, procurement, and construction progress. Either Party can request progress reports. If the Interconnection Customer determines the Transmission Provider's Interconnection Facilities will not be needed until after the In-Service Date, written notice must be provided to the Transmission Provider.

N-2Redacted NSPI Response to CA IRs 3 passages
NON-CONFIDENTIAL p. p. 13
NON-CONFIDENTIAL 1 Request IR-2: 7 (h) Assignment and Assumption of Power Purchase Agreement for Renewable Energy 8 between Interwind Corp. (formerly SkyPower), 324 NSL and Nova Scotia Power 9 Incorporated, dated December 23, 2009. Please...

AI summary The text outlines several requests and responses related to legal and contractual documents in a regulatory proceeding. It includes requests for assignments, conveyances, and agreements related to renewable energy and power purchase agreements, as well as a request for data demonstrating pricing superiority offered by EUS to 324 NSL.

BID COMPARISON p. p. 13
.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 1...

AI summary The text presents a line item from a bid comparison table, specifying a culvert with a 450mm diameter at a cost of 600 per meter. The context suggests this is part of infrastructure planning or procurement within a regulatory proceeding.

NON-CONFIDENTIAL p. p. 18
NON-CONFIDENTIAL 1 Request IR-20: 2 - 3 Please provide the Quarterly Development Reports for each project for the 4th quarter of - 4 2009 and the 1st and 2nd quarters of 2010, to supplement what was provided in NSUARB - 5 P-172 and NSUARB...

AI summary The request asks for quarterly development reports for specific projects from 2009 and 2010. The response indicates that only the latest independent power producer reports were provided in 2009 and that no further reports have been received for projects from the 2007 RFP.

N-3-(a)Redacted NSPI Response to UARB IR-1 to IR-12 (att 2) 25 passages
NSP chases after more green power p. p. 15
NSP chases after more green power

AI summary Nova Scotia Power Inc. (NSP) is pursuing increased investment in renewable energy sources to expand green power generation in the province, likely involving initiatives such as power purchase agreements (PPAs) or requests for proposals (RFPs) for renewable projects.

Utility falls short of its target on alternative energy p. p. 15
Utility falls short of its target on alternative energy By JUDY MYRDEN Business Reporter ŧ t Nova Scotia Power is pledging to generate more green electricity after failing to meet its own voluntary targets this year. The province's largest...

AI summary Nova Scotia Power Inc. (NSP) missed its 2009 renewable energy target of 100 MW due to a stalled wind project in Amherst, citing rising turbine costs and expired federal subsidies. NSP now aims to add 130 MW of renewable energy by 2009, hoping Acciona Canada's wind farm will proceed under a new request for proposal (RFP).

Renewable energy p. pp. 15-17
Renewable energy continued from / CL will be provided in January Some wind developers have ated electricity. The utility pays submit a price to be paid for the complained about the price NSP 6.5 to 7.2 cents per kilowatt hour. Mr. Tedesco...

AI summary Nova Scotia Power Inc. (NSP) faces challenges meeting renewable energy targets, with environmental groups urging legislative action. NSP warns of increased costs to comply with proposed regulations, estimating over $1.1 billion for new wind turbines. A bid by Scotian WindField Partners Corp. for 130 MW of renewable energy was rejected, while NSP highlights progress in adding 60 MW of renewable capacity.

2007 RFP for Renewable Energy p. p. 17
2007 RFP for Renewable Energy Pursuant to Section 3 of the Renewable Energy Standards Regulations (the "Regulations"), the Acting Minister of Energy by letter dated November 2, 2007, requested the Nova Scotia Utility and Review Board (the...

AI summary The Nova Scotia Utility and Review Board evaluated NSPI's 2007 RFP process for renewable energy, concluding it met RES standards. Key factors included oversubscription, rigorous project evaluation, performance security in PPAs, and effective threshold considerations. The Board emphasized the quality of proposals and risk allocation in the PPA template.

3. Items Covered by Board Staff p. p. 19
3. Items Covered by Board Staff The N.S. Government Renewable Energy Standards (RES) require that a certain percentage of NSPI energy sales be met by renewable energy sources, i.e. 5% by 2010 and 10% by 2013. The 2010 standard must be met...

AI summary Nova Scotia's Renewable Energy Standards (RES) require NSPI to source 5% of energy sales from renewables by 2010 via PPAs with IPPs. NSPI's ability to meet RES hinges on project developers' performance in achieving in-service dates and energy output. The text references a 2006 KEMA report on mitigating procurement risks in renewable energy contracts.

5. RFP Approaches to Lessen Contract Failure p. p. 19
5. RFP Approaches to Lessen Contract Failure Page 8 of the KEMA report lists a number of techniques to lessen the probability of contract failures. Board Staff conducted an assessment of how NSPI has applied these techniques in the 2007 RF...

AI summary The document outlines NSPI's use of 'Threshold Considerations' in its 2007 RFP process to filter viable projects, including preconditions like interconnection requests, PPA alignment, and environmental attribute rights. Board Staff assessed these criteria and concluded they effectively ensured proposal quality.

c. Request for Qualifications p. p. 19
c. Request for Qualifications This is an additional step to ensure serious bidders, as developers must demonstrate qualifications before being allowed to bid. NSPI states, in response to a Board Staff information request, that this separat...

AI summary NSPI argues that a separate Request for Qualifications (RFQ) step was unnecessary, as required information was included in their RFP. Board Staff agrees with NSPI's position that the RFP already contained the necessary details for evaluating bidders.

d. Due Diligence p. p. 19
d. Due Diligence KEMA states that due diligence involves evaluating projects on non-economic terms. The level of evaluation detail can vary from a cursory review to an in-depth evaluation of the likelihood of the project meeting its obliga...

AI summary KEMA defines due diligence as evaluating projects on non-economic terms, ranging from cursory to in-depth assessments. NSPI's RFP outlined evaluation criteria including project team experience, financing status, and environmental plans. Board Staff confirmed NSPI conducted an in-depth evaluation, deeming the criteria comprehensive and aligned with KEMA's standards.

e. Waiting List p. p. 19
e. Waiting List KEMA states that keeping a few proposals in reserve as backup can lessen the effects of contract failure. NSPI has followed this recommendation in two ways. - i. In early November NSPI sent letters of intent to the projects...

AI summary NSPI maintains a waiting list of backup projects to mitigate contract risks, including letters of intent and expansion options. Board Staff deems this acceptable. NSPI's RFP and PPA include deposit requirements aligned with KEMA's recommendations, ensuring performance security through letters of credit and liquidated damages clauses.

6. Board Staff review of Recommended Group Project Proposals p. p. 19
6. Board Staff review of Recommended Group Project Proposals Board Staff have reviewed the documentation provided in each of the project proposals for the Recommended Group. The purpose of the review was to arrive at our own opinion as to...

AI summary Board Staff reviewed Recommended Group Project Proposals, noting high quality due to developer experience, financing letters, and thorough environmental/community engagement. While confident in project success, they acknowledge risks like financing issues or opposition may cause some failures.

8. Conclusions p. p. 19
8. Conclusions In response to the Department of Energy's November 2,2007 request, Board Staff's opinion is that the process followed to date by NSPI is quite suitable to meet the RES set out in the Regulations. The main reasons for this op...

AI summary Board Staff concludes NSPI's process meets RES requirements through oversubscribed PPA capacity, rigorous project evaluation, and robust PPA performance measures. Key factors include project quality, threshold considerations, and financial safeguards like Performance Security.

VIA E-MAIL CONFIDENTIAL p. p. 19
VIA E-MAIL CONFIDENTIAL Mr. Peter W. Gurnham, Q.C., Chair, NOVA SCOTIA UTILITY AND REVIEW BOARD, 3 rd Floor, 1601 Lower Water Street, Halifax, Nova Scotia Dear Mr. Gurnham: Re: NSPI Renewable Energy Solicitation 2007 As requested by the Bo...

AI summary The Nova Scotia Utility and Review Board (UARB) reviewed the Power Purchase Agreement (PPA) for NSPI's 2007 renewable energy solicitation, concluding it was legally reasonable and suitable for inclusion in the RFP. The review focused on risk allocation to proponents and compared the PPA to existing contracts with independent power producers.

MCKINNON, PAMELA p. pp. 30-32
MCKINNON, PAMELA From: Sent: Cory Basil [[email protected]] Thursday, February 28, 2008 2:42 PM To: MCKINNON, PAMELA Subject: Sky Power - Digby Project Pricing Pam, Thanks for taking the time to speak with me over the past few days a...

AI summary Cory Basil of SkyPower Corp informs Pamela McKinnon of a revised price for the 30 MW Digby wind project, citing improved foreign exchange rates, lower interest rates, and enhanced wind assessments. The bid includes a 20-year PPA with a fixed levelized price and interconnection costs, targeting a 37.63% capacity factor and 98.9 GWh/year energy production.

If Skypower is prepared to enter into negotiations on this basis, please sign and return this letter to the undersigned. p. p. 32
If Skypower is prepared to enter into negotiations on this basis, please sign and return this letter to the undersigned. Yours truly, Pamela McKinnon Procurement Lead Date Name: Title: I have the authority to bind the Corporation. Nova Sco...

AI summary This document is a letter from Nova Scotia Power Inc. to Skypower, requesting negotiations on the Skypower Digby Project. It includes a table with contact information for the Procurement Lead and a statement of authority to bind the Corporation.

Agenda p. pp. 32-35
Agenda 1. Introductions 10 minutes NSPI 2. Project Review: 40-60 minutes - Project Team - Equipment Sourcing - Financing Progress - Queue Position - Price - Environmental Outlook/Plan - Community Engagement - Wind Resource - Ability to mee...

AI summary The agenda outlines a regulatory proceeding involving Nova Scotia Power Inc. (NSPI) and Skypower, covering project review aspects such as team composition, financing, community engagement, and wind resource assessments, followed by questions and next steps.

Recommendation p. p. 36
Recommendation It is recommended that a 20 year Power Purchase Agreement (PPA) be executed for 98.9 GWh / year of energy with Skypower Corp. at the commended that a 20 year Power Purchase Agreement (PPA) be executed for 98.9 GWh / year of...

AI summary The document recommends executing a 20-year Power Purchase Agreement (PPA) with Skypower Corp. to procure 98.9 GWh/year of energy. The recommendation emphasizes long-term procurement and specific energy output targets.

STRATEGIC PROCUREMENT SOURCING INITIATIVE Renewable Energy Sole Source Recommendation March 31, 2008 p. pp. 36-40
STRATEGIC PROCUREMENT SOURCING INITIATIVE Renewable Energy Sole Source Recommendation March 31, 2008 Skypower had originally proposed a 30 MW project at Digby, 25 years, see total evaluated cost including locational factor). Their revised...

AI summary Skypower revised its 20-year, 30 MW Digby wind project proposal to 98.9 GWh/year with adjusted pricing. Suez continues discussions with NSPI but has not yet provided firm terms. The initiative involves procurement and renewable energy sourcing under NSPI's oversight.

MCKINNON, PAMELA p. p. 41
MCKINNON, PAMELA From: EVERETT, MARK Sent: Tuesday, June 03, 2008 4:34 PM To: [email protected]; Richard Guttman Cc: JANEGA, RICHARD; MULDOON, DAN; MCKINNON, PAMELA Subject: Engineering & Procurement Agreement Attachments: Engineerin...

AI summary An email from Mark Everett to Pamela McKinnon and others discusses the Engineering & Procurement Agreement, referencing Section 9 of the Standard Generator Interconnection Procedures. The section outlines that a Transmission Provider may offer an E&P Agreement to begin engineering and procurement for long-lead items prior to executing a Generator Interconnection Agreement (GIA).

Dear Sirs: p. p. 94
Dear Sirs: Further to my email below, please find attached our revised version of the Purchase and Sale Agreement, which forms Appendix "A" to the amended offer. Also attached is our redline version of the Purchase and Sale Agreement and t...

AI summary Nova Scotia Power Inc. (NSPI) sends an amended offer and related documents (Purchase and Sale Agreement, Vesting Order) to Marathon and KPMG, requesting acknowledgment. The communication outlines document distribution and includes contact details for NSPI's legal representative.

RESOLVED THAT: p. p. 94
RESOLVED THAT: - 1. The Company is authorized and directed to finalize negotiations with SkyPower Corp. and conclude the purchase of its interest in the 30 megawatt wind project to be developed on Digby Neck, Nova Scotia (the "Transaction"...

AI summary The Board authorizes Emera Incorporated to finalize negotiations with SkyPower Corp. for purchasing a 30 MW wind project on Digby Neck, Nova Scotia. It also approves all prior actions related to the transaction and grants broad authority to execute agreements and take necessary steps to complete the purchase.

BORDEN LADNER GERVAIS LLP Barristers and Solicitors Scotia Plaza, 40 King Street West p. pp. 136-139
BORDEN LADNER GERVAIS LLP Barristers and Solicitors Scotia Plaza, 40 King Street West Toronto, Ontario M5H 3Y4 .. ':,' .... Michael J. MacNaughton TeL: (416) 367-6646 Fax: (416) 682-2837 LSUC # 25889U Roger Jaipargas Tel: (416) 367-6266 Fa...

AI summary NSPI entered a 20-year PPA with Skypower for a 30 MW Digby wind farm. After Skypower's bankruptcy under CCAA, NSPI's affiliate acquired the project. NSPI argues this acquisition preserves the project, avoiding higher costs from future competitive solicitations and ensuring customer benefits.

1. Medium and Large-Scale Projects p. p. 154
1. Medium and Large-Scale Projects Most of the new renewable energy needed to meet 2015 and 2020 goals will come from industrial-scale projects. The Renewable Electricity Plan calls for a minimum of 600 GWh of new medium to large-scale ren...

AI summary Nova Scotia's Renewable Electricity Plan prioritizes medium and large-scale renewable projects, with NSPI and independent power producers (IPPs) each contributing 600 GWh by 2020. Projects will be developed via UARB regulation for NSPI and competitive RFPs for IPPs, with a new Renewable Electricity Administrator (REA) managing the bidding process. Collaboration between NSPI and IPPs is allowed with NSPI's ownership capped at 49%.

Forest Biomass Used for Renewable Electricity p. p. 154
Forest Biomass Used for Renewable Electricity Procurement Requirements

AI summary The document section titled 'Forest Biomass Used for Renewable Electricity' outlines procurement requirements related to the use of forest biomass for generating renewable electricity in Nova Scotia. The content focuses on regulatory considerations for biomass procurement in the context of renewable energy initiatives.

Nova Scotia Power Inc. (NSPI) p. p. 165
Nova Scotia Power Inc. (NSPI) NSPI will continue to function as an integrated utility with an obligation to serve, legal responsibility to meet renewable energy targets,responsibility for system reliability compliance, and authority over p...

AI summary NSPI will maintain its role as an integrated utility with obligations to serve customers, meet renewable energy targets, ensure system reliability, and manage grid projects. To secure additional renewable electricity, NSPI may invest equity or purchase imported renewable energy at the lowest cost to customers.

Standard power purchase agreement p. p. 180
Standard power purchase agreement - 32 (1) The Minister, in consultation with NSPI shall prepare a standard form of power purchase agreement to be used for the purposes of this Part and have the form of power purchase agreement approved by...

AI summary The Minister, in consultation with NSPI, must prepare a standard power purchase agreement (PPA) form for this Part, approved by the Board. Parties may modify the standard PPA but must submit the form to the Minister.

N-3-(b)Redacted NSPI Response to UARB IR-12 (att 7-10) to IR-17 13 passages
SCOTIAN WINDFIELDS p. pp. 172-174
SCOTIAN WINDFIELDS Scotian WindFields Inc. was formed in January 2007 as a result of an agreement between eight Nova of Scotian community community-owned renewable energy owned companies formed under the CEDIF initiative - Ç Partnered with...

AI summary Scotian WindFields Inc., formed in 2007 under the CEDIF initiative, partners with SkyPower on a 30MW Digby project, develops solar hot water systems, and plans wind energy projects across 20,000+ acres in Nova Scotia and New Brunswick. The company also collaborates on biomass energy projects in Ontario.

BIDDING AND CONTRACT REQUIREMENTS p. p. 3
BIDDING AND CONTRACT REQUIREMENTS SkyPower Corp. Contract 090630.00 Digby Wind Power Project Information to Tenderers Section 00 21 00 Page 1 June 2009 5. Conditions of Tendering .1 Take full cognizance of content of all Contract Documents...

AI summary The document outlines bidding and contract requirements for the Digby Wind Power Project, including conditions for tendering, the obligation of tenderers to investigate site conditions, and procedures for clarifications and addenda to the contract documents.

E931 p. p. 3
E931 Item No. Description Unit of Measurement Estimated Quantity Unit Price Total Price NOTE: Tenders submitted by or on behalf of any Corporation must be signed and sealed in the name of such Corporation by a duly authorized officer or ag...

AI summary The document outlines the requirements for tender submissions in the Digby Wind Power Project, including the need for financial status verification, contract security, and insurance details. Key sections reference general conditions and contractual obligations.

BILL OF MATERIALS p. pp. 140-142
BILL OF MATERIALS (TABLE E9903-1) ITEM QTY. DESCRIPTION STD. OF ACCEPTANCE A10c 3 RISER POLE GAPLESS METAL-OXIDE VARISTER DISTRIBUTION-CLASS SURGE ARRESTER, 22.0kV MCOV, DESIGNED TO IEEE Std. C62.22, TESTED TO IEEE Std. C62.11, 675N-m CANT...

AI summary This document presents a bill of materials for electrical components and hardware used in power infrastructure, including surge arresters, bolts, washers, and mounting brackets. It includes specifications, standards, and details related to procurement and installation.

BILL OF MATERIALS p. p. 149
BILL OF MATERIALS Date Office Title: S313b each 15kV, 300A CUTOUT C/W LOAD-BREAK ATTACHMENT S411a each 27kV, 100A CUTOUT S411b each 27kV, 100A CUTOUT C/W LOAD-BREAK ATTACHMENT C730-213PB CHANCE S412a each 27kV, 200A CUTOUT S412b each 27kV,...

AI summary The document presents a bill of materials for the Digby Wind Power Project, listing various electrical components such as cutouts and disconnects with specific voltage and current ratings. The materials are part of the project's infrastructure planning and procurement process.

Quotation 090630-SP-E01 p. p. 15
Quotation 090630-SP-E01 1.2. From: We, the undersigned Bidder, having carefully examined the Quotation Documents in respect of quotations for the equipment listed in the Form of Quotation, and Specifications herewith submit in accordance w...

AI summary A bidder submits a quotation for equipment in accordance with the terms outlined in the Quotation Documents. The document is part of a procurement process, but lacks specific details about the equipment or terms.

2.0 BIDDER INFORMATION REQUIRED p. pp. 42-44
2.0 BIDDER INFORMATION REQUIRED A. CIRCUIT INTERRUPTER SPECIFICATION BIDDER'S REMARKS - Current Rating (A rms) - Wet Withstand Test at Operating Frequency, (V rms) - Dry Withstand Voltage at Operating Frequency, (V rms) - Full-Wave Impulse...

AI summary This section outlines the technical specifications required for a circuit interrupter as part of a procurement process. It includes details such as current ratings, withstand tests, insulation class, and physical dimensions.

13 RIGHT TO ACCEPT OR REJECT ANY QUOTATION p. pp. 60-61
13 RIGHT TO ACCEPT OR REJECT ANY QUOTATION - 13.1 The Purchaser reserves the right to waive any irregularity and to accept or reject any offer whatsoever. - 13.2 Quotations, which in the opinion of the Purchaser are considered to be inform...

AI summary This section outlines the Purchaser's right to accept or reject any quotation based on various criteria, including the technical, delivery, warranty, and commercial content of the tender packages. The Purchaser is not obligated to select the lowest bid and may reject any or all quotations if they are deemed informal or unbalanced.

SCHEDULE OF VENDOR TECHNICAL DATA p. pp. 98-136
SCHEDULE OF VENDOR TECHNICAL DATA > × FOF REV IEW FINAL ITEM: CONTI RACTOR: DOCUMENT TO BE ISSUED BY COPIES OF EACH COPY OF QUOTATION PRECEDE BY ELECTRONIC COPY/FAX ISSUE WEEK NO. REVIEW BY RETURN BY WEEK NO. • REVIEW BY RETURN BY WEEK NO....

AI summary This document outlines the schedule of vendor technical data required for a project, including various technical documents, forms, and specifications that must be submitted by vendors. It includes details such as the number of copies, review and return timelines, and other procedural requirements.

2 QUOTATIONS SUBMISSION p. pp. 106-107
2 QUOTATIONS SUBMISSION 2.1 Submit complete quotation—including completed Form of Quotation, Appendices 1-3 including, and proposed layout drawing(s)—in Adobe Portable Document Format ("pdf"), or similar electronic format approved by the E...

AI summary This section outlines the requirements for submitting quotations for a Pad Mounted Transformer as part of the Digby Wind Power Project. It specifies the format, delivery method, deadlines, and submission requirements, including the need for electronic and physical copies, and the consequences of non-compliance.

3 CLARIFICATION AND ADDENDA p. pp. 107-108
3 CLARIFICATION AND ADDENDA - 3.1 Notify Engineer of omissions, errors, or ambiguities found in the Quotation Documents. If Engineer considers that correction, explanation, or interpretation is necessary, a written addendum will be issued....

AI summary This section outlines procedures for addressing omissions, errors, or ambiguities in the Quotation Documents, specifying that written addenda will be issued if corrections or interpretations are needed. It also states that no oral explanations or instructions will be provided before equipment selection and provides contact information for Larry O'Keefe at CBCL Limited.

Section 3278 p. p. 160
- 2. DESCRIPTION OF .1 The document is presented in two parts. DOCUMENT Part I includes Information for Tenderers, Tender Form, and Form of Agreement. These sections are presented as a "standard format" which will require editing for each...

AI summary The document outlines a two-part structure for tender and contract documentation, specifying that Part I requires project-specific editing while Part II remains standardized and must only be amended through Supplementary Specifications. It emphasizes compliance with Construction Specifications Canada standards and provides details on subscription and copyright protections.

Section 3680 p. p. 160
using standardized bolting kits.

AI summary The text mentions the use of standardized bolting kits, which may relate to industry standards or procurement practices in utility operations.

06537Board Decision 2 passages
Submissions - Intervenors p. p. 0
UTHOUSE: I realize from your evidence so far that you were not involved in this decision, any of you on the panel. What's your understanding of why the construction contract wasn't put out to tender? MR. BENNETT: I don't know. I wasn't the...

AI summary Avon argues that the EUS construction contract should be subject to regulatory scrutiny, questioning why the contract wasn't put out to tender. NSPI's Mr. Bennett explains that the decision to work with EUS was made with an appreciation for the project's timeline and EUS's ability to deliver value.

Submissions - Intervenors p. p. 0
Submissions - Intervenors [60] Avon and the CA stress that the test for compliance, referring to section 2.2 of the Code, is that the transaction must be "... demonstrated through sound documented analysis to be the best available option f...

AI summary Avon and the CA argue that the EUS contract fails to meet the compliance test under section 2.2 of the Code, as there is no evidence it is the best option for NSPI's customers. They also claim that the lack of competitive bidding and NSPI's failure to follow Mr. Desdunes' suggestions indicates a lack of due diligence.

05666Letter enclosing NSPI's Responses to Information Requests 1 passage
Section 2 p. p. 0
ential (Board letter of July 30, 2010). The bases for the request for confidential treatment of these responses are therefore similar. This letter describes the details, in accordance with Rule 12(4). In certain IR responses, information h...

AI summary NSPI argues that certain information in IR responses should be treated confidentially to protect sensitive commercial terms and procurement strategies. This is to prevent suppliers from gaining an unfair advantage and increasing costs for NSPI and its customers.

06537Board Decision 2 passages
III CHRONOLOGY p. p. 0
III CHRONOLOGY [16] In NSPl's response to Board IR-1, a detailed description of the history of the DWP, and the events which subsequently occurred, was provided. For ease of reference, following is a summary of that information, along with...

AI summary NSPI issued a 2007 RFP for the DWP, and SkyPower submitted a response. However, NSPI did not select SkyPower due to the levelized cost proposed.

Submissions - Intervenors p. p. 0
Submissions - Intervenors [60] Avon and the CA stress that the test for compliance, referring to section 2.2 of the Code, is that the transaction must be "... demonstrated through sound documented analysis to be the best available option f...

AI summary Avon and the Chief Adjudicator argue that the EUS contract does not meet the compliance test under section 2.2 of the Code, as there was no competitive bidding and NSPI failed to pursue alternative bids suggested by SkyPower's Project Director.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →