IN THE MATTER OF: p. p. 0
IN THE MATTER OF: EfficiencyOne Supply Agreement – Behavioural Program Update

AI summary The document pertains to an update regarding the Behavioural Program under the EfficiencyOne Supply Agreement. It involves a regulatory proceeding in Nova Scotia, focusing on modifications or revisions to the program's terms, though specific details of the changes are not provided in the text.

96218Letter EOne re: Update 1 passage
Section 1 p. p. 0
James R. Gogan Direct +1 (902) 563 5920 [[email protected]](mailto:[email protected]) 292 Charlotte Street Suite 300 Sydney NS Canada B1P 1C7 Tel +1 (902) 563 1000 Fax +1 (902) 563 1113 Our File: 223853 December 19,...

AI summary EfficiencyOne (EOne) submits an update regarding a supply agreement with NS Power, focusing on shared use of the NS Power Bidgley platform and operation of EOne's behavioural program alongside NS Power's Customer Energy Management (CEM) module, in the regulatory proceeding M11647.

96424NSUARB (EOne) IR-1 to 5 1 passage
NOVA SCOTIA UTILITY AND REVIEW BOARD
NOVA SCOTIA UTILITY AND REVIEW BOARD IN THE MATTER OF: THE PUBLIC UTILITIES ACT - and - IN THE MATTER OF: AN APPICATION by EFFICIENCYONE (EOne) for approval of a Supply Agreement – Behavioural Program Update INFORMATION REQUESTS To: Effici...

AI summary The Nova Scotia Utility and Review Board has issued information requests to EfficiencyOne regarding its application for a Supply Agreement – Behavioural Program Update under the Public Utilities Act. Responses are due by February 4, 2025, with contact details provided for EfficiencyOne's counsel and the Board's Senior Advisor.

96678Letter EOne re: RIRs 1 passage
Section 1 p. p. 0
230 Brownlow Avenue, Suite 300 Dartmouth, Nova Scotia B3B 0G5 efficiencyone.com T +1 902 470 3500 F +1 902 470 3599 February 4, 2025 Attn: Crystal Henwood Regulatory Affairs Officer/Clerk Nova Scotia Utility and Review Board 3rd Floor, Sum...

AI summary EfficiencyOne submits responses to Information Requests (IRs) related to M12030, a Supply Agreement – Behavioural Program Update, received on January 13, 2025. The letter, dated February 4, 2025, is addressed to Crystal Henwood at the Nova Scotia Utility and Review Board, with Gina Thompson of EfficiencyOne as the sender and James Gogan of McInnes Cooper as the CC recipient.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →