Topic/Matter Intersection

Topic:"Procurement Practices" in M12592

Matter: Nova Scotia Power Inc. - CI 47751 – ECC Dynamic Line Rating Implementation - $2,148,364
2 passages 2 documents

Procurement Practices across all matters →

N-2NSPI (NSEB) RIR 1 to 20 - Redacted 1 passage
REDACTED p. p. 19
REDACTED 1 Request IR-5: 2 3 In March of 2024, NS Power conducted an RFP seeking a suitable vendor for this 4 implementation. Eight vendors responded and all responses were reviewed in detail. The 5 final decision and contract award was ba...

AI summary NS Power conducted an RFP in March 2024 for a vendor to implement a Dynamic Line Rating (DLR) system. Eight vendors responded, and the selection was based on meeting key RFP criteria and best suitability for NS Power operations. The response includes a summary of the tender evaluation results.

100485NSEB (NSPI) IR 1 to 20 - PDF 1 passage
Request IR-5:
Request IR-5: - "In March of 2024, NS Power conducted an RFP seeking a suitable vendor for this - implementation. Eight vendors responded and all responses were reviewed in detail. The final - decision and contract award was based on meeti...

AI summary NS Power conducted an RFP in March 2024 for a vendor implementation, with eight vendors responding. The final decision was based on meeting RFP criteria and suitability to NS Power operations. The request seeks details on the tender evaluation, technical reports, maintenance costs, and similar technology use by other FERC-regulated utilities.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →