Matter: Nova Scotia Power - Cybersecurity Accountability IN THE MATTER OF AN INQUIRY about the impact of the cyber incident on NOVA SCOTIA POWER INCORPORATED’s collection and retention of customer information, customer service and communications, billing processes and regulatory matters
4 passages 4 documents

Procurement Practices across all matters →

100853NS Power's Monthly Update #2 (M12273) 1 passage
Previous Expected Timeline Activity Current Expected Timeline p. p. 6
Previous Expected Timeline Activity Current Expected Timeline Q4 2023 - Q2 2024 Identify requirements for and completion Complete of competitive solicitation for Planning and Procurement partner. Q3 2024 - Q1 2025 Develop plan for CIS Repl...

AI summary The timeline for the CIS Replacement Project outlines key activities from Q4 2023 to Q2 2028, including identifying requirements, developing plans, issuing an RFP, and launching the new system. The project was paused during the proposal evaluation phase, with the NSEB decision expected in Q1 2026 and the new CIS system launch in Q2 2029.

101156NSPI Monthly Update Report #6 (M12273) 1 passage
The following projects experienced adjustments to their completion timeline. An overview of the changes and associated rationale is outlined below: p. p. 5
The following projects experienced adjustments to their completion timeline. An overview of the changes and associated rationale is outlined below: Pillar Project Summary of Change Rationale Administration Approval required for a credit on...

AI summary The document outlines adjustments to project completion timelines, citing issues such as invoice disputes, approval requirements, and discrepancies between purchase orders and invoices. These delays are attributed to administrative, procurement, and receiving challenges.

102373NSPI Monthly Update Report #9 (M12273) 1 passage
The following projects experienced adjustments to their completion timeline. An overview of the changes and associated rationale is outlined below: p. p. 6
The following projects experienced adjustments to their completion timeline. An overview of the changes and associated rationale is outlined below: Pillar Project Summary of Change Rationale Administration • Approval required for a credit...

AI summary The text outlines adjustments to project timelines due to various administrative and procurement issues, including invoice disputes, approval requirements, and discrepancies between purchase orders and invoices.

103205NSPI Monthly Update Report #11 (M12273) 1 passage
The following projects experienced adjustments to their completion timeline. An overview of the changes and associated rationale is outlined below:
The following projects experienced adjustments to their completion timeline. An overview of the changes and associated rationale is outlined below: Pillar Project Summary of Change Rationale 5% 4% 4% 5% 4% 6% 1% 15% 12% Procurement 274 77...

AI summary The document outlines adjustments to project completion timelines, with changes in percentages and reasons for delays such as administrative holds, procurement issues, and receiving delays. Specific reasons for holds include invoice disputes, missing purchase orders, and tax approvals.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →