CONFIDENTIAL (Attachment Only) 1 Request IR-3: 2 3 (a) Was an engineering assessment performed that recommended the proposed overhaul 4 of the components? If yes, please provide the report. If not, please explain why no 5 assessment was co...
AI summary The response to Request IR-3 indicates that no engineering assessment was performed for the proposed overhaul of turbine components, as the decision was based on maintenance strategy targets. Contract estimates were derived from previous project quotes and reviewed by subject matter experts. Risks covered by the 20% contingency are not explicitly detailed.