n, the storm rider was amended to provide customers with a refund of underspent amounts from 2026 onwards. This provision does not, therefore, apply to the 2025 level 3 and 4 storm OM&G underspending. In its decision about an authorization...
AI summary The 2025 Storm Restoration Cost Report discusses NS Power's implementation of cost control measures, including the creation of a Contractor Oversight position and the use of per diems to reduce expenses. The Board had previously ordered NS Power to implement such measures and report on their effectiveness, which NS Power has now addressed in its 2025 report.