Matter: Nova Scotia Power Inc. - CI C0083591 – IR746 Petpeswick Community Solar - $0 (U&U)2026 Q1 Capital Reports
2 passages 1 document

Procurement Practices across all matters →

N-1CI C0083591 – IR746 Petpeswick Community Solar - $0 - Redacted 2 passages
6.2 Procurement Security for Long Lead Equipment and Scoping p. p. 26
6.2 Procurement Security for Long Lead Equipment and Scoping The following facilities are required to be purchased with procurement security funds: • Primary metering rack consisting of three metering class potential transformers rated 7,2...

AI summary Section 6.2 outlines procurement requirements for long-lead equipment, specifying technical specifications for primary metering racks including potential and current transformers. The text emphasizes security funding obligations for these facilities.

6.3 Facilities Procured by the Interconnection Customer p. pp. 26-27
6.3 Facilities Procured by the Interconnection Customer The Interconnection Customer is responsible for procurement of all facilities required for the operation of the solar installation.

AI summary The Interconnection Customer bears full responsibility for procuring all facilities necessary for the solar installation's operation, including infrastructure, equipment, and associated systems.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →