Topic/Matter Intersection

Topic:"Program Requirements" in M12619

Matter: Nova Scotia Power Inc. - 2026 Annual Capital Expenditure (ACE) Plan - $284 million
7 passages 6 documents

Program Requirements across all matters →

N-1Application - Redacted 1 passage
Section 1306
1 projects to date: both IR-673 and IR-669 are expected to be in service in the near-term as per the 2 forecast COD table (Figure 3 above). In addition, both IR-668 and IR-677 are making progress in 3 engineering and construction to achiev...

AI summary The document discusses the progress of projects IR-673, IR-669, IR-668, and IR-677, and details the Green Choice Program (GCP), established under the 2022 Electricity Act amendments. The GCP aims to procure 1,500–2,000 GWh of low-impact renewable energy annually for large consumers, supporting Nova Scotia’s 2030 decarbonization goals. NS Power collaborates with the Department of Energy (DOE) and executes participant agreements for the program.

N-3NSPI (CA) RIR 1 to 32 - Redacted 1 passage
7 p. p. 23
7 PDM Element Purpose/Objective Equivalent Practice/Process Triggering Event Reason for difference Project Inception Form This element is to provide information related to the project, including items such as location, scope, operational c...

AI summary The text outlines the Program Documentation Method (PDM) elements and their purposes, noting that no equivalent processes exist for these elements due to the routine and repetitive nature of the projects involved. This highlights differences in documentation practices between standard procedures and the specific context of these projects.

103410Decision 1 passage
2.4.1.1 Findings p. pp. 32-33
2.4.1.1 Findings [87] Given the growth and evolution of the Routine Program, the Board considers that interested party review of the CEJC Routine provisions is warranted. Among other matters, that review should consider whether enhanced ju...

AI summary The Board recommends a review of the CEJC Routine Program due to its growth and evolution, emphasizing the need for enhanced justification in cases of significant changes in expenditure, work, or standards.

100691NSEB (NSPI) IR 1 to 202 - Word 1 passage
Section 55
on page 455, the proposed change to the requirements directing when to apply for a FIN is an increase of the underspent threshold from -5%/ $250,000 to -10%/ $500,000 in order to exclude contingency. 1. Please provide stakeholder feedback...

AI summary The text discusses proposed changes to the FIN approval threshold and stakeholder feedback, as well as the definition of 'scope' in the ACE Plan application. It raises questions about NS Power's consideration of alternative approaches and notification procedures for significant underspending.

103410Decision 2 passages
2.4.1.1 Findings p. pp. 32-33
2.4.1.1 Findings [87] Given the growth and evolution of the Routine Program, the Board considers that interested party review of the CEJC Routine provisions is warranted. Among other matters, that review should consider whether enhanced ju...

AI summary The Board recommends a review of the CEJC Routine Program due to its growth and evolution, emphasizing the need for enhanced justification in cases of significant changes, increased expenditure, or adoption of new standards.

2.4.2 Directives p. p. 33
2.4.2 Directives [88] The Board finds that the sustained growth and evolving composition of the Routine Program require requires enhanced prospective transparency. The additional information is intended to preserve the regulatory efficienc...

AI summary The Board requires NS Power to enhance transparency and reporting for the Routine Program, including detailed financial and operational data, to ensure regulatory efficiency and proper cost justification. This includes rolling five-year comparisons, cost breakdowns, and explanations for changes in expenditures.

20260422-1Hearing Transcript — 04/22/2026 (Revised Transcript - Refiled May 20, 2026) 1 passage
NS POWER PANEL 437 Questions, (Murphy)
NS POWER PANEL 437 Questions, (Murphy) 1 So as a part of this capital 12 13 14 15 16 Please provide the number of outage events, by year, for each feeder listed in attachment 1. MEMBER MURPHY: And if you scroll 17 down, Rob? 18 BY MEMBER M...

AI summary The document outlines a regulatory proceeding involving NS Power, where specific questions are raised regarding outage events and condition ratings for feeders listed in Attachment 1, as well as the review of an IR response to a revised IR-19. The discussion centers on compliance and accuracy of data provided.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →