Matter: Nova Scotia Power Inc. - CI C0053699 – Renewable to Retail Implementation - $5,644,468
2 passages 2 documents

Programs And Customers across all matters →

N-4NSPI (REI) RIR 1 to 22 1 passage
- 6 As mentioned in part (b), NS Power does not have access to the original estimate details. p. p. 36
- 6 As mentioned in part (b), NS Power does not have access to the original estimate details. 1 Request IR-12: 2 3 Reference: N-1, C0053699 Renewable to Retail Implementation Project, pages 2-3 of 6. 4 5 (a) Please break down the $581,816...

AI summary The text discusses a request for a breakdown of a financial variance related to the Renewable to Retail Implementation Project, including administrative overhead, data integration, and testing complexity. It also asks about schedule extension impacts and mitigation steps taken by NS Power. Further requests focus on software systems involved in the project and their cybersecurity-related cost impacts.

100718NSEB (NSPI) IR 1 to 15 - Word 1 passage
Section 5
ct Implementation team before the LRS was granted its interconnection requests? 1. Please explain the start date of February 2023 1. Why was an application not brought forward for approval sooner? On page 2, NS Power states that it “conduc...

AI summary The text contains a series of questions directed at NS Power regarding the implementation of the RtR Market, including the start date of February 2023, the use of existing tools for reporting, stakeholder requirements, and the competitive procurement process for the project.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →