The following table provides a summary of the schedule of work included in the three capital projects.
p. p. 16
The following table provides a summary of the schedule of work included in the three capital projects. Task Lingan Unit 1 Pt Tupper Unit 2 Trenton Unit 6 Submission to DARB September 2007 Authorize vendor to proceed November 2007 Delivery...
AI summary The text provides a table summarizing the schedule of work for three capital projects, including key milestones such as submission to DARB, authorization to proceed, delivery to site, start of outage, completion of work, and guarantee testing for each project.