Matter: P-886 Nova Scotia Power Inc. (NSPI) Rate Application 2007
2 passages 2 documents

Project Schedule across all matters →

N-2-bRIRs 1 to 26 - AEC to NSPI - REDACTED (Large File - MB) 1 passage
Project timeline
Project timeline March Program design April Program design; Bid process May Delivery agents under contract June - Aug Initial home visits Aug - Nov Second home visits Nov Follow-up visits Dec Evaluation report Going forward - what LDCs can...

AI summary The document outlines a project timeline for a program involving delivery agents and home visits, scheduled from March to December. The process includes program design, a bid process, contracting delivery agents, conducting two rounds of home visits with follow-up visits, and culminating in an evaluation report. The text also introduces a section regarding the future actions available to Low-Income Communities (LDCs).

N-44RIRs 76 to 136 - CA to NSPI - REDACTED (Large File - 19 MB) 1 passage
Key Issues:
Key Issues: - ☐ Date for final UARB report moved to Jan 8; workplan adjusted to reflect this accelerated schedule; final design of future operating capability will occur after UARB report has been finalized

AI summary The date for the final UARB report has been moved to January 8, with the workplan adjusted to accommodate the accelerated schedule. The final design of future operating capability will occur after the UARB report is finalized.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →