Attachment 12 – NRCan SG 2021/22 Annual Performance Report • Attachment 13 – NRCan EVID 2021/22 Annual Performance Report • Attachment 14 – SIF 2020/21 Annual Performance Benefits Report 6 Overall Project Update The Project remains on trac...
AI summary The project is on track and within budget, with testing, data collection, and analysis progressing as outlined in previous reports. The timeline has been revised to allow for additional time in testing and evaluation without affecting costs, scope, or project risks.
including processing, analysis and management; 4) Facility expenses for seminars, conference room rentals, etc. (excluding hospitality); 5) License fees and permits; and 6) Field testing services. . REDACTED (CONFIDENTIAL INFORMATION REMOV...
AI summary The document includes a certification and project update from Nova Scotia Power, detailing project tasks completed and expected in the next quarter, alignment with the contribution agreement, and the absence of environmental permits required during the quarter ending September 30, 2022.