Matter: Board Inquiry into Nova Scotia Power's Cybersecurity Incident
5 passages 3 documents

Project Schedule across all matters →

102372NSPI Monthly Update Report #9 2 passages
Preamble p. pp. 0-6
� The dates shown in this Gantt chart represent the current planned schedule for the Restoration Program Office (RPO) initiatives. These timelines are subject to change based on evolving priorities, resource availability, and unforeseen de...

AI summary The text provides information about the current planned schedule for the Restoration Program Office (RPO) initiatives, as depicted in a Gantt chart. The timelines are subject to change due to evolving priorities, resource availability, and unforeseen dependencies.

The following projects experienced adjustments to their completion timeline. An overview of the changes and associated rationale is outlined below: p. p. 6
The following projects experienced adjustments to their completion timeline. An overview of the changes and associated rationale is outlined below: Pillar Project Summary of Change Rationale Affected Regulatory Matters Report 2 - October 1...

AI summary The document outlines adjustments to the completion timelines of various regulatory projects, including the Capital and A ce Plan and the CIS Replacement Project, with updates and expected submissions to the NSEB in 2026.

102710NSPI Monthly Update Report #10 2 passages
Preamble p. pp. 0-5
� The dates shown in this Gantt chart represent the current planned schedule for the Restoration Program Office (RPO) initiatives. These timelines are subject to change based on evolving priorities, resource availability, and unforeseen de...

AI summary The document provides a Gantt chart showing the current planned schedule for the Restoration Program Office (RPO) initiatives. These timelines are subject to change depending on evolving priorities, resource availability, and unforeseen dependencies.

The following projects experienced adjustments to their completion timeline. An overview of the changes and associated rationale is outlined below: p. p. 5
The following projects experienced adjustments to their completion timeline. An overview of the changes and associated rationale is outlined below: Pillar Project Summary of Change Rationale Sy stem Planning System Planning Introduced NA N...

AI summary The document outlines adjustments to project timelines, including the transition of IRP Modelling to the IESO-NS and the resolution of an issue related to the Maritime Link Project, with updated reporting by NSPML in its October 15, 2025, Quarterly Report.

103204NSPI Monthly Update Report #11 1 passage
Preamble
� The dates shown in this Gantt chart represent the current planned schedule for the Restoration Program Office (RPO) initiatives. These timelines are subject to change based on evolving priorities, resource availability, and unforeseen de...

AI summary The text outlines the current planned schedule for the Restoration Program Office (RPO) initiatives, noting that these timelines are subject to change based on evolving priorities, resource availability, and unforeseen dependencies.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →