HomeProject ScheduleM12418Evidence
Topic/Matter Intersection

Topic:"Project Schedule" in M12418

Matter: Nova Scotia Power Inc. - CI 49036 – HYD - Avon 2 Controls Upgrade - $1,073,463
5 passages 3 documents

Project Schedule across all matters →

N-1Application - CI 49036 - HYD Avon 2 Controls Upgrade - Redacted 1 passage
Document No: XXX-XX-XXXX-XXXX p. p. 8
tem Discipline Drawings Preliminary (P) Mechanical Discipline Drawings Not Applicable (NA) Auxiliary Electrical Design & Drawings Preliminary (P) Auxiliary Mechanical Design & Drawings Not Applicable (NA) Protection & Controls System Desig...

AI summary The document outlines various project disciplines and their design statuses, including preliminary and not applicable statuses for different engineering aspects. It also references a Project Cost Estimate Input Checklist and Maturity Matrix, indicating a focus on project planning and cost estimation.

N-2NSPI (NSEB) RIR 1 to 7 3 passages
1 Request IR-1:
NON-CONFIDENTIAL 1 Request IR-1: 20 (i) Long lead item identification. 21 c. Schedule creation 22 (i) Critical path identification. 23 d. Resource planning 24 25 5. Implementation 26 a. Procurement 27 (i) Acquisition of all specified mater...

AI summary The document outlines a structured plan for implementing a project, including steps such as identifying long lead items, creating schedules, resource planning, procurement, decommissioning, construction, commissioning, training, enhanced support, post-upgrade support, and maintenance planning.

11
11 Category Lesson Learned Addressing Proactively – How? Schedule Commissioning took longer than anticipated. Build sufficient lead time into the schedule for commissioning. Develop a detailed commissioning plan with step-by-step activitie...

AI summary The text outlines lessons learned from a project, highlighting delays due to insufficient scheduling, resource allocation, and testing. It emphasizes the need for detailed planning, including commissioning, temporary power arrangements, and early identification of long-lead items to prevent delays.

Section 12
Request IR-5: Page 2 under Contingency Statement explains that changes from the schedule may result in overtime and spending the project's contingency budget. How much time has NS Power budgeted for this project? (a) Please compare the amo...

AI summary The request inquires about the time budgeted for a project by NS Power and asks for a comparison with previous similar projects. The response is not provided in the text.

99992Board Decision Letter 1 passage
REDACTED (CONFIDENTIAL INFORMATION REMOVED) p. p. 1
REDACTED (CONFIDENTIAL INFORMATION REMOVED) P va Scotia OWER Emera Company NSEB APPROVAL SHEET Project Title: HYD - Avon 2 Controls Upgrade CI Number: 49036 Date: August 5, 2025 Expenditure Profil le Type of Filing Year Budget Amount Proje...

AI summary The document outlines the expenditure profile for the HYD - Avon 2 Controls Upgrade project, including budget amounts, project estimates, and approvals over multiple years. The project was initially included in the 2025 ACE Plan as a carryover but should have been categorized as a project under $1,000,000. The Nova Scotia Energy Board approved the project on November 17, 2025.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →