DATE FILED: December 9, 2024 Page 27 of 54
p. p. 121
DATE FILED: December 9, 2024 Page 27 of 54 1 6.2 Battery Storage & Renewable Integration Resources 2 3 The 2030 Clean Power Plan calls for deployments of grid-scale storage in Nova Scotia. In 2024 4 150 MW of 4-hour storage capacity was ap...
AI summary The text discusses the approval and progress of the NS Power Battery Storage Project (ECEI) in Nova Scotia, including the approval of capital costs, construction activities, and commissioning dates for the battery storage sites. It also mentions the 2030 Clean Power Plan and future storage capacity additions.