Topic:"Project Schedule" in M12600

Matter: Nova Scotia Power - Cybersecurity Accountability IN THE MATTER OF AN INQUIRY about the impact of the cyber incident on NOVA SCOTIA POWER INCORPORATED’s collection and retention of customer information, customer service and communications, billing processes and regulatory matters
9 passages 7 documents

Project Schedule across all matters →

100853NS Power's Monthly Update #2 (M12273) 1 passage
CIS Replacement Project p. pp. 5-6
CIS Replacement Project As noted by the NSEB in its letter of September 17, 2025, the CIS replacement capital project has been delayed by the Incident. NS Power said its investigation into the cybersecurity incident "could impact the direc...

AI summary The CIS replacement project has been delayed due to a cybersecurity incident, as noted by the NSEB and confirmed by NS Power. NS Power provided an updated project timeline in its compliance filing for M11884.

100856NS Power's Monthly Update #5 (M12273) 1 passage
Preamble p. pp. 0-6
The dates shown in this Gantt chart represent the current planned schedule for the Restoration Program Office (RPO) initiatives. These timelines are subject to change based on evolving priorities, resource availability, and unforeseen depe...

AI summary The text provides information about the current planned schedule for the Restoration Program Office (RPO) initiatives, as depicted in a Gantt chart. The timelines are subject to change based on evolving priorities, resource availability, and unforeseen dependencies.

101156NSPI Monthly Update Report #6 (M12273) 1 passage
Preamble p. pp. 0-5
The dates shown in this Gantt chart represent the current planned schedule for the Restoration Program Office (RPO) initiatives. These timelines are subject to change based on evolving priorities, resource availability, and unforeseen depe...

AI summary The text discusses the current planned schedule for the Restoration Program Office (RPO) initiatives, as shown in a Gantt chart. The timelines are subject to change based on evolving priorities, resource availability, and unforeseen dependencies.

101623NSPI Monthly Update Report #7 (M12273) 2 passages
Preamble p. pp. 0-6
� The dates shown in this Gantt chart represent the current planned schedule for the Restoration Program Office (RPO) initiatives. These timelines are subject to change based on evolving priorities, resource availability, and unforeseen de...

AI summary The document presents a Gantt chart showing the current planned schedule for the Restoration Program Office (RPO) initiatives, with the note that these timelines are subject to change due to evolving priorities, resource availability, and unforeseen dependencies.

The following projects experienced adjustments to their completion timeline. An overview of the changes and associated rationale is outlined below: p. p. 6
The following projects experienced adjustments to their completion timeline. An overview of the changes and associated rationale is outlined below: Pillar Project Summary of Change Rationale Rates-Related Matters System Planning System Pla...

AI summary The document outlines adjustments to project timelines, including the transition of IRP Modelling to IESO-NS and the resolution of the Maritime Link Project's capital cost allocation issue, as reported by NSPML in its October 15, 2025, Quarterly Report.

102002NSPI Monthly Update Report #8 (M12273) 1 passage
Section 12 p. pp. 0-5
� The dates shown in this Gantt chart represent the current planned schedule for the Restoration Program Office (RPO) initiatives. These timelines are subject to change based on evolving priorities, resource availability, and unforeseen de...

AI summary The document provides a visual representation of the current planned schedule for the Restoration Program Office (RPO) initiatives, with dates subject to change based on evolving priorities, resource availability, and unforeseen dependencies.

102373NSPI Monthly Update Report #9 (M12273) 2 passages
Preamble p. pp. 0-6
� The dates shown in this Gantt chart represent the current planned schedule for the Restoration Program Office (RPO) initiatives. These timelines are subject to change based on evolving priorities, resource availability, and unforeseen de...

AI summary The text provides a Gantt chart illustrating the current planned schedule for the Restoration Program Office (RPO) initiatives, noting that these timelines are subject to change based on evolving priorities, resource availability, and unforeseen dependencies.

The following projects experienced adjustments to their completion timeline. An overview of the changes and associated rationale is outlined below: p. p. 6
The following projects experienced adjustments to their completion timeline. An overview of the changes and associated rationale is outlined below: Pillar Project Summary of Change Rationale System Plan nning System Planning Introduced NA...

AI summary The document outlines adjustments to project timelines, including the transition of IRP Modelling to the IESO-NS and the resolution of an issue related to the Maritime Link Project, with updated reporting by NSPML in its October 15, 2025, Quarterly Report.

103205NSPI Monthly Update Report #11 (M12273) 1 passage
The following projects experienced adjustments to their completion timeline. An overview of the changes and associated rationale is outlined below:
The following projects experienced adjustments to their completion timeline. An overview of the changes and associated rationale is outlined below: Pillar Project Summary of Change Rationale Dispatch Study Action Plan Quarterly Update Intr...

AI summary The document outlines adjustments to the completion timelines of various projects, including the Dispatch Study Action Plan, Hosting Capacity Map, and others. Some projects are now live or in the Hypercare Phase, with forecasts for restoration of normal activities by late 2026. The timeline changes are accompanied by rationales such as software integration and data requirements.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →