Matter: Nova Scotia Power Dispatch Study Action Plan – Quarterly Update – Q1 2026
1 passage 1 document

Project Schedule across all matters →

N-1Report 1 passage
p. p. 4
S Milestone Planned Status Q4 2025 Status Q1 2026 Requirements & Design 2025 Q3 100% 100% D Technical Realization 2025 Q4 75% 90% D System Integration Testing 2025 Q4 0% 25% End-User Testing 2026 Q1 0% 25% Training & Deployment Planning 20...

AI summary The document outlines the progress of a project as of January 2026, showing the status of various milestones such as technical realization, system integration testing, and end-user testing. Most milestones are either fully completed or in progress, with some still at the beginning stages.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →