2.2 KEY INPUTS Site Visit Details Comments Date of site visit March 6, 2026 Project Schedule Financial Close December 19, 2025 Achieved Onslow Substation Construction Complete May 31, 2027 On Schedule Salisbury Substation Construction Comp...
AI summary This section outlines key inputs related to the Onslow Substation and other transmission projects, including construction schedules, financial close dates, and project costs. The current forecast final cost matches the original project budget, and the project is on schedule.
Activity Scheduled Date Status Financial Close 19-Dec-25 Achieved Material Procurement Substation Breakers Deliveries Complete On Schedule OPGW Deliveries Complete On Schedule Optical Ground Wire Deliveries Complete On Schedule Conductor D...
AI summary The document outlines the progress of various activities related to the Wasoqonatl Transmission Line Project, indicating that several key milestones such as financial close and material procurement have been achieved or are on schedule. BTY Consultancy Group Inc. expresses confidence in the project's timeline.