Request IR-3:
Request IR-3: Reference : Exh. N-1, Section 5.4.1 - a) Please provide a list of all high-voltage equipment (including but not limited to transformers and circuit breakers) required for the NS-NB Reliability Intertie and the procurement sta...
AI summary Request IR-3 seeks information about the procurement status of high-voltage equipment for the NS-NB Reliability Intertie, risk mitigation plans for potential delays, contingency plans if the project is not completed by 2028, and whether outages of the existing 345 kV line will be required.