HomeProject ScheduleM12961Evidence
Topic/Matter Intersection

Topic:"Project Schedule" in M12961

Matter: Nova Scotia Power Inc. - CI C0061550 – L5031 Replacements and Upgrades – Hubbards to East Chester - $6,957,058 (ATO)
4 passages 2 documents

Project Schedule across all matters →

N-2NSPI (NSEB) RIRs 1-10 - Redacted 3 passages
Section 1
CI C0061550 – L5031 Replacements and Upgrades – Hubbards to East Chester (NSEB M12961) NSPI Responses to NSEB Information Requests

AI summary The document contains NSPI's responses to NSEB information requests regarding the L5031 Replacements and Upgrades project from Hubbards to East Chester, identified as NSEB M12961.

CI C0061550 – L5031 Replacements and Upgrades – Hubbards to East Chester (NSEB M12961) NSPI Responses to NSEB Information Requests
CI C0061550 – L5031 Replacements and Upgrades – Hubbards to East Chester (NSEB M12961) NSPI Responses to NSEB Information Requests 1 Request IR-4: L5031-083 2Pole: 69- T-H(2) Tangent 118 10 40 40 1/0 No Suspensio n Vertical 12 Porcelain (B...

AI summary The document presents a regulatory proceeding involving NSPI's responses to NSEB information requests regarding the L5031 Replacements and Upgrades project from Hubbards to East Chester. It includes details on infrastructure, such as pole replacements and transformer usage, and questions about project costs and variances.

Section 183
3 (d) The ultimate cost to complete the project was not known in December 2025, when the 2026 4 ACE Plan forecast was submitted. The Issued for Construction (IFC) engineering design 5 for the bypass structures was not finalized until March...

AI summary The project faced delays and changes in planning, including the abandonment of a mobile transformer unit and the decision to construct three bypass structures. The start of construction was delayed due to transmission line outage restrictions and the finalization of engineering designs.

103363NSEB (NSPI) IR 11 to 18 1 passage
Request IR-13:
Request IR-13: In response to IR-5 a), NS Power states: NS Power owns three 25 MVA mobile transformers. To ensure emergency preparedness across the system, at least one 25 MVA mobile transformer must remain available for deployment and sho...

AI summary NS Power is responding to a request regarding the use of mobile transformers for emergency preparedness and project timelines. The transformer deployment on L-5031 was removed to ensure availability for emergency use, and the L5031 Replacements and Upgrades project has faced delays due to transmission line outage restrictions.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →