HomePrudence ReviewsM12786Evidence
Topic/Matter Intersection

Topic:"Prudence Reviews" in M12786

Matter: Nova Scotia Power Inc. - 2025 Storm Restoration Cost Report
1 passage 1 document

Prudence Reviews across all matters →

101812IG (NSPI) IR-1 to 10 1 passage
Section 5
Any deficiencies, limitations, or failures identified post- 9 event. 10 (c) Please quantify, where possible, the cost savings attributed to: 11 (i) Standardized storm contractors; 12 (ii) Per diem meal reimbursement practices; and 13 (iii)...

AI summary The document outlines requests for quantifying cost savings from storm contractor practices, explaining contractor invoice validation, and clarifying NSPI's storm level declarations. It also seeks expanded data on predicted vs. actual restoration times and the use of impact forecasts in emergency decisions.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →