3.2.4.1 Class of Estimate - The Control Centre cost estimates were developed by IBM as a Class 3 Budgetary Estimate in - accordance with AACE estimating standards. The estimate after contingency carries an - expected accuracy range of -15%...
AI summary IBM developed the Control Centre cost estimates as a Class 3 Budgetary Estimate, adhering to AACE standards. The estimate, which carries an expected accuracy range of -15% to +20% after contingency, was derived from a mix of vendor data, Nova Scotia Power information, analogous projects, and industry benchmarks. IBM asserts the estimate is sufficient for current decision-making, with plans to refine precision to Class 2 and Class 1 levels as the project moves into detailed design and procurement.
12 Figure 8: NPV Sensitivity Analysis - Full Project Net Present Value (NPV) Scenarios - Full Project NPV IRR Base Case Scenario +$219M 37% High Case (-15% Capex, +30% benefits) +$328M 54% Low Case (+20% Capex, -40% benefits) +$?3M 16% Cap...
AI summary The document presents a sensitivity analysis of the Net Present Value (NPV) and Internal Rate of Return (IRR) for a full project under various scenarios. It evaluates the project's financial viability against fluctuations in capital expenditures (Capex), realized benefits, and timing. The Base Case Scenario shows a positive NPV of $219M with a 37% IRR. Notably, a 'Low Case' involving a 20% Capex increase and 40% benefit reduction results in a negative NPV of -$3M, while a scenario with both 50% higher capital costs and 50% lower benefits yields a marginal NPV of $21M.
1 Figure 9: NPV Sensitivity Analysis - Steady State 1 Net Present Value (NPV) Scenarios - essents: 1000000 Phases 2A and 2B NPV IRR Base Case Scenario +$110M 30% High Case (-15% Capex, +30% benefits) +$173M 46% Low Case (+20% Capex, -40% b...
AI summary The document presents a Net Present Value (NPV) and Internal Rate of Return (IRR) sensitivity analysis for Phases 2A and 2B of a project. It evaluates various scenarios, including adjustments for capital expenditure (Capex) fluctuations, variations in projected benefits, delays in benefit realization, and the impact of carbon removal. The analysis shows that the project remains viable in most scenarios, though a simultaneous 50% increase in capital costs and a 50% decrease in benefits results in a negative NPV.
4. Additional Stress Scenarios - Capex +50% : Assumes a 50% increase in capital costs, resulting in an NPV of +$188M and an IRR of 26%. - Benefits -50%: Assumes a 50% reduction in benefits, resulting in an NPV of +$52M and an IRR of 15%. -...
AI summary The text presents a stress test of the Net Present Value (NPV) and Internal Rate of Return (IRR) for a proposed program under various unfavorable scenarios. These include a 50% increase in capital costs, a 50% reduction in benefits, a two-year delay in benefit realization, and the removal of carbon benefits. The analysis concludes that the program maintains a positive NPV across all tested scenarios, demonstrating a robust and sound economic case for the investment, with primary value drivers being the timing of benefits and capital costs.
Net Present Value (NPV) Scenarios – Phases 2A and 2B NPV IRR Base Case Scenario +$110M 30% High Case (-15% Capex, +30% benefits) +$173M 46% Low Case (+20% Capex, -40% benefits) +$26M 11% Capex +50% +$88 20% Benefits -50% +$16M 10% Capital...
AI summary The document presents a sensitivity analysis of Net Present Value (NPV) and Internal Rate of Return (IRR) for various project phases (2A and 2B). It evaluates the financial viability of the project under multiple scenarios, including a Base Case, High Case (reduced Capex, increased benefits), Low Case (increased Capex, reduced benefits), and scenarios involving delayed benefits, carbon removal, and significant fluctuations in capital costs and benefits. The findings indicate that the project's profitability is highly sensitive to capital expenditure and benefit realization rates.
Benefit (CADm) Low Mid. High (1) Shifting cost overrun risk 47 67 87 (2) Reduced resource cost from competitive procurement - 67 135 (3A) Reduced production costs from accelerated deployment 186 274 363 (3B) Accelerated CapEx deployment (f...
AI summary The document presents a quantitative benefit-cost analysis of Nova Scotia Power's 2025 Annual Capital Expenditure Plan, categorized into Low, Mid, and High scenarios. It evaluates various factors including cost overrun risk mitigation, competitive procurement savings, accelerated deployment benefits, and avoided carbon costs. The analysis also accounts for financial disbenefits such as lost synergies from planner-operator separation and accelerated CapEx deployment. Total estimated benefits range from $500 million in the Low scenario to $2,361 million in the High scenario.
s, and filed evidence from its consultant addressing various aspects of HRWC's application. The Board ultimately approved the application, subject to various significant disallowances and adjustments. The CA is pleased with the results it...
AI summary The Consumer Advocate (CA) expresses satisfaction with the outcomes achieved for its customer class regarding the Halifax Regional Water Commission's (HRWC) application. The Board approved the application but included significant disallowances and adjustments. The CA intends to remain involved in future proceedings and provides a detailed summary of its participation and the relevant matters addressed.