Matter: NSPI CI# 38819 - $7,452,511 - 51V Tremont Circuit Breaker & Bus
1 passage 1 document

Prudency Review across all matters →

N-2NSPI Redacted Responses to Information Requests 1 passage
Section 1 p. p. 0
November 22, 2010 Ms. Nancy McNeil Regulatory Affairs Officer/Clerk Nova Scotia Utility and Review Board 3 rd Floor, 1601 Lower Water Street P.O. Box 1692, Unit "M" Halifax, NS B3J 3S3 Re: CI 38819 – 51V Tremont Circuit Breaker & Bus - Res...

AI summary NSPI has provided responses to information requests regarding a capital item, stating that certain details like the substation single line diagram and contractor names are confidential for system security and competitive reasons. NSPI emphasizes that maintaining confidentiality benefits customers as rates are cost-based and that information is shared with the Board and non-conflicting intervenors in confidence for prudence review.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →