NS Power's contractor performed a test to assess the poles' condition and administered retreatment when necessary. Since the testing is done at the time of retreatment, the full scope of poles requiring treatment was not known in advance....
AI summary NS Power's project to retreat poles was delayed due to remote locations, adverse terrain, and a cyber incident. The project was completed a year late, and the final cost of $791,054 was approved by the Board. The project reduced the number of poles retreated and lowered the average cost per pole.