Why do this project now?
p. p. 8
Why do this project now? The original damper system that was repaired where there were damages on an interim basis in Q3 2022 has reached its end-of-life, and without mitigation the conductor is at risk of damage from ongoing aeolian vibra...
AI summary The damper system repaired in Q3 2022 has reached end-of-life, risking conductor damage from aeolian vibration. Immediate replacement is needed to avoid public safety risks over highways 104/19 and system failure in the Cape Breton Export Corridor. Additional damage discovered in Q1 2025 accelerated the project from 2026 to 2025.