Topic/Matter Intersection

Topic:"Public Utilities Act Nova Scotia" in M03669

Matter: E-ENSC-R-10 - Efficiency Nova Scotia Corporation - Electricity Demand Side Management Plan for 2012A request by Efficiency Nova Scotia for approval of a $43.7 million Demand Side Management plan for the 2012 operating year.  (Also see Matter Nos. M04538 and M04539)
17 passages 16 documents

Public Utilities Act Nova Scotia across all matters →

E-1Evidence - 2012 DSM Plan 2/28/2011 1 passage
Efficiency Nova Scotia Corporation p. p. 3
Efficiency Nova Scotia Corporation IN THE MATTER OF The Public Utilities Act , R.S.N.S. 1989, c.380, as amended. - and - IN THE MATTER OF An Application to Approve Efficiency Nova Scotia Corporation's Electricity Demand Side Management (DS...

AI summary The document outlines a regulatory proceeding involving Efficiency Nova Scotia Corporation's application to approve its 2012 Electricity Demand Side Management (DSM) Plan under the Public Utilities Act. The matter pertains to the approval process for energy efficiency initiatives.

E-7ENSC (Multeese) IR-1 to IR-31 3/29/2011 1 passage
PROGRAM AND EXPENDITURES p. p. 48
PROGRAM AND EXPENDITURES - 35 The Corporation shall submit to the Review Board for approval an electricity demand-side management program for one or more calendar years, at the time and in the manner required by the Review Board, commencin...

AI summary The document outlines the requirements for the Corporation to submit an electricity demand-side management program for approval by the Review Board, ensuring cost allocation is just and reasonable. It also details the Review Board's supervisory role over the Corporation and the application of the Public Utilities Act with specific exceptions.

E-12Evidence of Mel Whalen, Multeese Consulting, Board Consultant 4/8/2011 1 passage
IN THE MATTER OF THE PUBLIC UTILITIES ACT, R.S.N.S 1989, c380, AS AMENDED
IN THE MATTER OF THE PUBLIC UTILITIES ACT, R.S.N.S 1989, c380, AS AMENDED And IN THE MATTER OF AN APPLICATION BY EFFICIENCY NOVA SCOTIA CORPORATION FOR APPROVAL OF ITS ELECTRICITY DEMAND SIDE MANAGEMENT PLAN FOR 2012

AI summary This document pertains to a regulatory proceeding under the Public Utilities Act, concerning Efficiency Nova Scotia Corporation's application for approval of its 2012 Electricity Demand Side Management Plan.

E-14Reply Evidence of Efficiency Nova Scotia Corporation 4/13/2011 1 passage
Efficiency Nova Scotia Corporation
Efficiency Nova Scotia Corporation IN THE MATTER OF The Public Utilities Act , R.S.N.S. 1989, c.380, as amended. - and - IN THE MATTER OF An Application to Approve Efficiency Nova Scotia Corporation's Electricity Demand Side Management (DS...

AI summary The document pertains to an application by Efficiency Nova Scotia Corporation to approve its 2012 Electricity Demand Side Management (DSM) Plan under the Public Utilities Act. The proceeding involves regulatory review of the plan's alignment with legislative requirements and energy efficiency goals.

E-19Proof of Advertising 4/18/2011 1 passage
IN THE MATTER OF THE PUBLIC UTILITIES ACT p. p. 2
IN THE MATTER OF THE PUBLIC UTILITIES ACT - and- IN THE MATTER OF AN APPLICATION by EFFICIENCY NOVA SCOTIA CORPORATION for Approval of its Electricity Demand Side Management Plan for 2012 BEFORE: Peter W. Gurnham, Q.C., Chair

AI summary The document outlines an application by Efficiency Nova Scotia Corporation for approval of its 2012 Electricity Demand Side Management Plan under the Public Utilities Act. The proceeding is presided over by Peter W. Gurnham, Q.C., Chair.

05676Hearing Order 11/4/2010 1 passage
IN THE MATTER OF THE PUBLIC UTILITIES ACT
IN THE MATTER OF THE PUBLIC UTILITIES ACT - and- IN THE MATTER OF AN APPLICATION by EFFICIENCY NOVA SCOTIA CORPORATION for Approval of its Electricity Demand Side Management Plan for 2012 BEFORE: Peter W. Gurnham, Q.C., Chair

AI summary The document outlines a regulatory proceeding under the Public Utilities Act involving Efficiency Nova Scotia Corporation's application for approval of its 2012 Electricity Demand Side Management Plan. The proceeding is presided over by Peter W. Gurnham, Q.C., Chair.

07314Board Decision 6/30/2011 1 passage
[11 ] The relevant provisions of the ENSC Act are: p. p. 0
emand-side management programs with a view to restraining electricity demand and use; and - (b) may engage in energy efficiency and conservation programs other than electricity demand-side management. - 31 (1) Subject to the approval of th...

AI summary The ENSC Act outlines the Efficiency Nova Scotia Corporation's (ENSC) authority to manage demand-side management (DSM) and energy efficiency programs. It mandates the Review Board's approval of annual DSM assessments, cost allocation between DSM and other programs, and oversight of ENSC's compliance. The Public Utilities Act applies to this oversight, ensuring just and reasonable cost distribution.

IR-1 to IR-13 issued by Tim Woolf, Synapse Energy Economics, Inc. (Board Counsel Consultant)06609 3/17/2011 1 passage
NOVA SCOTIA UTILITY AND REVIEW BOARD p. p. 7
NOVA SCOTIA UTILITY AND REVIEW BOARD IN THE MATTER OF: THE PUBLIC UTILITIES ACT -and- IN THE MATTER OF: AN APPLICATION by Efficiency Nova Scotia Corporation ("ENSe") for approval of 2012 Electricity Demand Side Management ("DSM") Plan for...

AI summary Efficiency Nova Scotia Corporation (ENSe) seeks approval for its 2012 Electricity Demand Side Management (DSM) Plan under the Public Utilities Act. The application focuses on energy efficiency initiatives to manage electricity demand.

05676Hearing Order 11/4/2010 1 passage
IN THE MATTER OF THE PUBLIC UTILITIES ACT
IN THE MATTER OF THE PUBLIC UTILITIES ACT - and- IN THE MATTER OF AN APPLICATION by EFFICIENCY NOVA SCOTIA CORPORATION for Approval of its Electricity Demand Side Management Plan for 2012 BEFORE: Peter W. Gurnham, Q.C., Chair

AI summary The document outlines a regulatory proceeding under the Public Utilities Act involving Efficiency Nova Scotia Corporation's application for approval of its 2012 Electricity Demand Side Management Plan. The proceeding is before Peter W. Gurnham, Q.C., Chair, focusing on the corporation's proposal for energy efficiency initiatives.

06563Preliminary Issues List 3/7/2011 1 passage
THE MATTER OF THE PUBLIC UTILITIES ACT p. p. 0
THE MATTER OF THE PUBLIC UTILITIES ACT - and - IN THE MATTER OF AN APPLICATION by EFFICIENCY NOVA SCOTIA CORPORATION for Approval of its Electricity Demand Side Management Plan for 2012

AI summary The document outlines a regulatory proceeding under the Public Utilities Act, involving Efficiency Nova Scotia Corporation's application for approval of its 2012 Electricity Demand Side Management Plan. The matter pertains to energy efficiency initiatives and regulatory oversight of utility programs.

06564Final Issues List 3/21/2011 1 passage
Nova Scotia Utility and Review Board IN THE MATTER OF THE PUBLIC UTILITIES ACT p. p. 0
Nova Scotia Utility and Review Board IN THE MATTER OF THE PUBLIC UTILITIES ACT - and- IN THE MATTER OF AN APPLICATION by EFFICIENCY NOVA SCOTIA CORPORATION for Approval of its Electricity Demand Side Management Plan for 2012

AI summary The Nova Scotia Utility and Review Board is considering an application by Efficiency Nova Scotia Corporation for approval of its 2012 Electricity Demand Side Management Plan under the Public Utilities Act. The proceeding involves regulatory review of the plan's alignment with energy efficiency goals.

06935NPB Final Submission 5/13/2011 1 passage
BEFORE THE NOVA SCOTIA UTILITY AND REVIEW BOARD
BEFORE THE NOVA SCOTIA UTILITY AND REVIEW BOARD IN THE MATTER OF: ) The Public Utilities Act, R.S.N.S. 1989, ) c. ) 380, as amended ) – and – IN THE MATTER OF: An Application by Efficiency Nova Scotia Corporation for Approval of its Electr...

AI summary A written submission by NewPage Port Hawkesbury Corp. and Bowater Mersey Paper Company Ltd. relates to Efficiency Nova Scotia Corporation's application for approval of its 2012 Electricity Demand Side Management Plan under the Public Utilities Act.

06951ENSC Closing Submission 5/13/2011 2 passages
Efficiency Nova Scotia Corporation
Efficiency Nova Scotia Corporation IN THE MATTER OF The Public Utilities Act , R.S.N.S. 1989, c.380, as amended. - and - IN THE MATTER OF An Application to Approve Efficiency Nova Scotia Corporation's Electricity Demand Side Management (DS...

AI summary The document outlines an application to approve Efficiency Nova Scotia Corporation's 2012 Electricity Demand Side Management (DSM) Plan under the Public Utilities Act.

1 ENSC sees continued value and support in having the PDWG continue throughout 2011,
19 See, for example, Exhibit [E-12], Supra Note 8, Page 3, Lines 5-6. 20 Exhibit [E-1], Supra Note 7, Page 29. 21 Exhibit [E-12], Supra Note 8, Page 2, Lines 26-28. 1 ENSC sees continued value and support in having the PDWG continue throug...

AI summary ENSC supports continuing the PDWG throughout 2011 and proposes a multi-year performance-driven regulatory model. ENSC seeks approval from the UARB and the Board to assess options for implementing this model. Board Counsel Mel Whalen shows tacit agreement, subject to legislative confirmation. The Board Chair raises questions about the Public Utilities Act's compatibility with performance-based regulation.

06953NSDOE/NSE Closing Submission 5/13/2011 1 passage
Performance-Based Model p. p. 0
Performance-Based Model NSDOE supports ENSC's proposal to engage the DARB and stakeholders in 2011 to assess the possibility ofadopting a performance based model for the delivery and oversight ofDSM programs. As part of this process, NSDOE...

AI summary NSDOE supports ENSC's proposal to engage DARB and stakeholders in 2011 to assess a performance-based model for DSM programs. NSDOE agrees with the Board Chair to investigate whether the Public Utilities Act permits performance-based oversight of DSM, potentially requiring legislative changes.

07314Board Decision 6/30/2011 1 passage
[11 ] The relevant provisions of the ENSC Act are: p. p. 0
emand-side management programs with a view to restraining electricity demand and use; and - (b) may engage in energy efficiency and conservation programs other than electricity demand-side management. - 31 (1) Subject to the approval of th...

AI summary The ENSC Act outlines the Corporation's authority to manage demand-side management (DSM) programs, requiring Review Board approval for annual assessments and program submissions. The Board must ensure cost allocation between DSM and other energy efficiency programs is just and reasonable, with oversight of the Corporation's compliance.

07662Status Report on 2010 Evaluation Recommendations and 2010 Savings Verification Study Action Items 7/29/2011 1 passage
Efficiency Nova Scotia Corporation
Efficiency Nova Scotia Corporation IN THE MATTER OF The Public Utilities Act , R.S.N.S. 1989, c.380, as amended. - and - IN THE MATTER OF An Application to Approve Efficiency Nova Scotia Corporation's Electricity Demand Side Management (DS...

AI summary The document outlines an application by Efficiency Nova Scotia Corporation to approve its 2012 Electricity Demand Side Management (DSM) Plan under the Public Utilities Act. The proceeding references the specific application matter number E-ENSC-R-10.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →