Matter: P-141 - Nova Scotia Power Inc. - Request Approval of the 2011 Annually Adjusted Rates (AAR's)Request approval of 2011 Annually Adjusted Rates: 1) Load Following (LF) portion of the GRLF Tariff; 2) One Part Real Time Price (1P-RTP) Fixed Cost Adders; 3) Wholesale Market Back-Up/Top-up (BUTU) Tariff; 4) Wholesale Market Non-Dispatchable Supplier Spill (Spill) Tariff
13 passages 12 documents

Public Utilities Act Nova Scotia across all matters →

N-1NSPI Redacted 2011 Annually Adjusted Rates 11/5/2010 2 passages
UTILITY AND REVIEW BOARD p. p. 0
UTILITY AND REVIEW BOARD IN THE MATTER OF: THE PUBLIC UTILITIES ACT, R.S.N.S., 1989, c.380 - and -

AI summary This document pertains to a regulatory proceeding under the Public Utilities Act in Nova Scotia. It outlines the context of the Utility and Review Board's involvement in matters related to public utilities.

PROVINCE OF NOVA SCOTIA UTILITY REVIEW BOARD p. p. 27
PROVINCE OF NOVA SCOTIA UTILITY REVIEW BOARD IN THE MATTER OF: THE PUBLIC UTILITIES ACT, R.S.N.S., 1989, c.380 - and -

AI summary This document is the beginning of a regulatory proceeding under the Public Utilities Act in Nova Scotia. It sets the context for the proceeding and includes the title of the matter being reviewed.

N-2Refiled 2011 Annually Adjusted Rates (AAR's) 12/8/2010 1 passage
PROVINCE OF NOVA SCOTIA UTILITY REVIEW BOARD p. pp. 31-53
PROVINCE OF NOVA SCOTIA UTILITY REVIEW BOARD IN THE MATTER OF: THE PUBLIC UTILITIES ACT, R.S.N.S., 1989, c.380 - and -

AI summary The document is an introduction to a regulatory proceeding under the Public Utilities Act in Nova Scotia. It sets the context for the Utility Review Board's involvement in the matter.

06039Board Order approving 2011 One Part Distribution Voltage Real Time Pricing Tariff 1 passage
IN THE MATTER OF THE PUBLIC UTILITIES ACT p. p. 2
IN THE MATTER OF THE PUBLIC UTILITIES ACT - and- IN THE MATTER OF THE REQUEST BY NOVA SCOTIA POWER INCORPORATED FOR APPROVAL OF THE FIXED COST ADDERS FOR THE ONE PART DISTRIBUTION VOLTAGE REAL TIME PRICING TARIFF BEFORE: ~argaretA. M. Shea...

AI summary This proceeding involves Nova Scotia Power Incorporated's request for approval of fixed cost adders for the One Part Distribution Voltage Real Time Pricing Tariff under the Public Utilities Act.

06041Board Order approving 2011 One Part Extra High Voltage Real Time Pricing Tariff 1 passage
IN THE MATTER OF THE PUBLIC UTILITIES ACT p. p. 2
IN THE MATTER OF THE PUBLIC UTILITIES ACT - and - IN THE MATTER OF THE REQUEST BY NOVA SCOTIA POWER INCORPORATED FOR APPROVAL OF THE FIXED COST ADDERS FOR THE O"'~E PART EXTRA HIGH VOLTAGE REAL TIME PRICING TARIFF BEFORE: Margaret A. M. Sh...

AI summary This document pertains to a regulatory proceeding under the Public Utilities Act, concerning Nova Scotia Power Incorporated's request for approval of fixed cost adders for the O'~E Part Extra High Voltage Real Time Pricing Tariff, before Vice-chair Margaret A. M. Shears.

06042Board Order approving 2011 Wholesale Market Non-Dispatchable Supplier Spill Tariff 1 passage
IN THE MATTER OF THE PUBLIC UTILITIES ACT
IN THE MATTER OF THE PUBLIC UTILITIES ACT - and- IN THE MATTER OF THE REQUEST BY NOVA SCOTIA POWER INCORPORATED FOR APPROVAL OF THE MONTHLY CUSTOMER CHARGE FOR THE WHOLESALE MARKET NON-DISPATCHABLE SUPPLIER SPILL TARIFF BEFORE: Margaret A....

AI summary This document pertains to a regulatory proceeding concerning Nova Scotia Power Incorporated's request for approval of a monthly customer charge under the Wholesale Market Non-Dispatchable Supplier Spill Tariff, as governed by the Public Utilities Act.

06043Board Order approving 2011 Wholesale Market Backup/Top-up Service Tariff 1 passage
IN THE MATTER OF THE PUBLIC UTILITIES ACT p. p. 2
IN THE MATTER OF THE PUBLIC UTILITIES ACT - and- IN THE MATTER OF THE REQUEST BY NOVA SCOTIA POWER INCORPORATED FOR APPROVAL OF THE MONTHLY CUSTOP,,1ER CHARGE FOR THE WHOLESALE MARKET BACKUP/TOP..UP SERVICE TARIFF BEFORE: Margaret A. M. Sh...

AI summary This document pertains to a regulatory proceeding under the Public Utilities Act, concerning Nova Scotia Power Incorporated's request for approval of a monthly customer charge for the Wholesale Market Backup/Top-Up Service Tariff, before Vice-chair Margaret A. M. Shears.

06038Board Order approving 2011 Generation Replacement Load Following Rate 1 passage
IN THE MATTER OF THE PUBLIC UTILITIES ACT
IN THE MATTER OF THE PUBLIC UTILITIES ACT - and - IN THE MATTER OF THE REQUEST BY NOVA SCOTIA POWER INCORPORATED FOR APPROVAL OF AN ENERGY CHARGE FOR THE OPTiONAL GENERATION LOAD FOLLOWING RATE OF THE GENERATION REPLACEMENT AND LOAD FOLLOW...

AI summary This document outlines a regulatory proceeding under the Public Utilities Act, concerning Nova Scotia Power Incorporated's request for approval of an energy charge for optional generation load following rate under the Generation Replacement and Load Following Tariff.

06039Board Order approving 2011 One Part Distribution Voltage Real Time Pricing Tariff 1 passage
IN THE MATTER OF THE PUBLIC UTILITIES ACT p. p. 2
IN THE MATTER OF THE PUBLIC UTILITIES ACT - and- IN THE MATTER OF THE REQUEST BY NOVA SCOTIA POWER INCORPORATED FOR APPROVAL OF THE FIXED COST ADDERS FOR THE ONE PART DISTRIBUTION VOLTAGE REAL TIME PRICING TARIFF BEFORE: ~argaretA. M. Shea...

AI summary This proceeding concerns Nova Scotia Power Incorporated's request for approval of fixed cost adders for the One Part Distribution Voltage Real Time Pricing Tariff under the Public Utilities Act.

06040Board Order approving 2011 One Part High Voltage Real Time Pricing Tariff 1 passage
IN THE MATTER OF THE PUBLIC UTILITIES ACT p. p. 2
IN THE MATTER OF THE PUBLIC UTILITIES ACT - and - IN THE MATTER OF THE REQUEST BY NOVA SCOTIA POWER INCORPORATED FOR APPROVAL OF THE FIXED COST ADDERS FOR THE ONE PART HIGH VOLTAGE REAL TIME PRICING TARIFF BEFORE: Margaret A. M. Shears, Q....

AI summary This document pertains to a regulatory proceeding under the Public Utilities Act, concerning Nova Scotia Power Incorporated's request for approval of fixed cost adders for a specific high voltage real-time pricing tariff.

06041Board Order approving 2011 One Part Extra High Voltage Real Time Pricing Tariff 1 passage
IN THE MATTER OF THE PUBLIC UTILITIES ACT p. p. 2
IN THE MATTER OF THE PUBLIC UTILITIES ACT - and - IN THE MATTER OF THE REQUEST BY NOVA SCOTIA POWER INCORPORATED FOR APPROVAL OF THE FIXED COST ADDERS FOR THE O"'~E PART EXTRA HIGH VOLTAGE REAL TIME PRICING TARIFF BEFORE: Margaret A. M. Sh...

AI summary This document outlines a regulatory proceeding concerning Nova Scotia Power Incorporated's request for approval of fixed cost adders for the O'~E Part Extra High Voltage Real Time Pricing Tariff, before Margaret A. M. Shears, a.c., Vice-chair.

06042Board Order approving 2011 Wholesale Market Non-Dispatchable Supplier Spill Tariff 1 passage
IN THE MATTER OF THE PUBLIC UTILITIES ACT
IN THE MATTER OF THE PUBLIC UTILITIES ACT - and- IN THE MATTER OF THE REQUEST BY NOVA SCOTIA POWER INCORPORATED FOR APPROVAL OF THE MONTHLY CUSTOMER CHARGE FOR THE WHOLESALE MARKET NON-DISPATCHABLE SUPPLIER SPILL TARIFF BEFORE: Margaret A....

AI summary This document outlines a regulatory proceeding concerning Nova Scotia Power Incorporated's request for approval of a monthly customer charge for the Wholesale Market Non-Dispatchable Supplier Spill Tariff under the Public Utilities Act.

06043Board Order approving 2011 Wholesale Market Backup/Top-up Service Tariff 1 passage
IN THE MATTER OF THE PUBLIC UTILITIES ACT p. p. 2
IN THE MATTER OF THE PUBLIC UTILITIES ACT - and- IN THE MATTER OF THE REQUEST BY NOVA SCOTIA POWER INCORPORATED FOR APPROVAL OF THE MONTHLY CUSTOP,,1ER CHARGE FOR THE WHOLESALE MARKET BACKUP/TOP..UP SERVICE TARIFF BEFORE: Margaret A. M. Sh...

AI summary This document pertains to a regulatory proceeding under the Public Utilities Act, involving Nova Scotia Power Incorporated's request for approval of a monthly customer charge for the Wholesale Market Backup/Top-Up Service Tariff.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →