Matter: NSP Maritime Link Inc. (NSPML) - Application to Review the Holdback Mechanism
12 passages 12 documents

Public Utilities Act Nova Scotia across all matters →

N-8Evidence - CA 1 passage
NOVA SCOTIA ENERGY BOARD p. p. 2
NOVA SCOTIA ENERGY BOARD IN THE MATTER OF: The Public Utilities Act and the Maritime Link Act and the Maritime Link Cost Recovery Process Regulations - and – IN THE MATTER OF: An application by NSP Maritime Link Inc. to end the holdback me...

AI summary The Nova Scotia Energy Board is considering an application by NSP Maritime Link Inc. to terminate a holdback mechanism under the Public Utilities Act and Maritime Link Cost Recovery Process Regulations. John D. Wilson, representing the Consumer Advocate, provided evidence on behalf of Grid Strategies, LLC, in Matter M11009.

N-9BW (IG) RIR 1 to 5 1 passage
NOVA SCOTIA ENERGY BOARD
NOVA SCOTIA ENERGY BOARD IN THE MATTER OF: The Public Utilities Act and the Maritime Link Act and the Maritime Link Cost Recovery Process Regulations -and- IN THE MATTER OF: An Application by NSP Maritime Link Inc. to end the holdback mech...

AI summary The Nova Scotia Energy Board addresses two matters: the Public Utilities Act and Maritime Link Act, and an application by NSP Maritime Link Inc. to terminate a holdback mechanism under parameters set by the Nova Scotia Utility and Review Board in Matter 11009.

N-11Rebuttal Evidence - NSPML 1 passage
IN THE MATTER OF p. p. 1
IN THE MATTER OF The Public Utilities Act, R.S.N.S 1989, c. 380, as amended and the The Maritime Link Act, S.N.S 2012 c.9 and the Maritime Link Cost Recovery Process Regulations, N.S. Reg. 189/2012

AI summary This document pertains to regulatory proceedings under the Public Utilities Act and the Maritime Link Act, including the Maritime Link Cost Recovery Process Regulations. It sets the legal and regulatory framework for the proceedings.

100872Hearing Order 1 passage
NOVA SCOTIA ENERGY BOARD
NOVA SCOTIA ENERGY BOARD IN THE MATTER OF the PUBLIC UTILITIES ACT and the MARITIME LINK ACT and the MARITIME LINK COST RECOVERY PROCESS REGULATIONS – and – IN THE MATTER OF AN APPLICATION by NSP MARITIME LINK INC. to end the holdback mech...

AI summary The Nova Scotia Energy Board is considering an application by NSP Maritime Link Inc. to terminate a holdback mechanism under the Public Utilities Act and Maritime Link Cost Recovery Process Regulations, referencing Matter M11009. The proceeding involves the Nova Scotia Utility and Review Board's parameters.

101452Amended Hearing Order - timeline has been amended 1 passage
NOVA SCOTIA ENERGY BOARD
NOVA SCOTIA ENERGY BOARD IN THE MATTER OF the PUBLIC UTILITIES ACT and the MARITIME LINK ACT and the MARITIME LINK COST RECOVERY PROCESS REGULATIONS – and – IN THE MATTER OF AN APPLICATION by NSP MARITIME LINK INC. to end the holdback mech...

AI summary The Nova Scotia Energy Board is considering an application by NSP Maritime Link Inc. to terminate the holdback mechanism under the Public Utilities Act and Maritime Link Cost Recovery Process Regulations, referencing prior board matter M11009. The proceeding involves regulatory oversight of cost recovery processes.

100872Hearing Order 1 passage
NOVA SCOTIA ENERGY BOARD
NOVA SCOTIA ENERGY BOARD IN THE MATTER OF the PUBLIC UTILITIES ACT and the MARITIME LINK ACT and the MARITIME LINK COST RECOVERY PROCESS REGULATIONS – and – IN THE MATTER OF AN APPLICATION by NSP MARITIME LINK INC. to end the holdback mech...

AI summary The Nova Scotia Energy Board is considering an application by NSP Maritime Link Inc. to terminate the holdback mechanism under the Public Utilities Act and Maritime Link Cost Recovery Process Regulations, referencing parameters set in Matter M11009. The proceeding involves the Maritime Link Act and regulatory compliance.

100897Notice of Intervention - NSPI 1 passage
NOTICE OF INTERVENTION
NOTICE OF INTERVENTION Take Notice that Nova Scotia Power Inc. ("NS Power") requests to intervene in this proceeding in accordance with Rule 11(1) of the Board Regulatory Rules. NS Power is a regulated public utility engaged in the generat...

AI summary Nova Scotia Power Inc. (NS Power) seeks to intervene in a regulatory proceeding, citing that the outcome will impact its payments to NSP Maritime Link Inc. (NSPML). NS Power, a regulated public utility, intends to participate in the oral hearing and address issues relevant to its role as a public utility under the Public Utilities Act.

100901Notice of Intervention - SBA 1 passage
NOVA SCOTIA ENERGY BOARD
NOVA SCOTIA ENERGY BOARD IN THE MATTER OF: The Public Utilities Act and the Maritime Link Act and the Maritime Link Cost Recovery Process Regulations - and - IN THE MATTER OF: An Application by NSP Maritime Link Inc. to end the holdback me...

AI summary The Nova Scotia Energy Board is addressing an application by NSP Maritime Link Inc. to terminate the holdback mechanism under the Public Utilities Act and Maritime Link Cost Recovery Process Regulations, referencing parameters set by the Nova Scotia Utility and Review Board in Matter Ml1009.

101306NSEB (NSPML) IR 1 to 19 - PDF 1 passage
1 M12696
1 M12696 2 3 4 NOVA SCOTIA UTILITY AND REVIEW BOARD 5 6 IN THE MATTER OF: The Public Utilities Act and the MARITIME LINK ACT and 7 8 the MARITIME LINK COST RECOVERY PROCESS REGULATIONS 9 10 11 – and – 12 13 IN THE MATTER OF: AN APPLICATION...

AI summary The Nova Scotia Utility and Review Board is considering an application by NSP Maritime Link Inc. to end a holdback mechanism under the Public Utilities Act and Maritime Link Act. The Consumer Advocate has issued information requests to NSP Maritime Link, with responses due April 9, 2026, regarding the cost recovery process.

101310SBA (NSPML) IR 1 to 6 - PDF 1 passage
1 M12696
1 M12696 2 3 NOVA SCOTIA ENERGY BOARD 4 5 6 7 IN THE MATTER OF: The Public Utilities Act, R.S.N.S. 1989, c.380, as amended and the MARITIME LINK ACT and the MARITIME LINK COST RECOVERY PROCESS REGULATIONS 8 9 10 11 IN THE MATTER OF: An app...

AI summary This document is an information request from the Small Business Advocate to Shellie Woolham of NSP Maritime Link, regarding an application to end the holdback mechanism under the Public Utilities Act and Maritime Link Cost Recovery Process Regulations. Responses are due by April 9, 2026.

102698Submission - NSPML 1 passage
IN THE MATTER OF p. p. 2
IN THE MATTER OF The Public Utilities Act, R.S.N.S 1989, c. 380, as amended and the The Maritime Link Act, S.N.S 2012 c.9 and the Maritime Link Cost Recovery Process Regulations, N.S. Reg. 189/2012

AI summary The document pertains to regulatory proceedings under the Public Utilities Act, the Maritime Link Act, and the Maritime Link Cost Recovery Process Regulations. These legal frameworks govern utility operations and cost recovery processes in Nova Scotia.

102909Reply Submission - NSPML 1 passage
IN THE MATTER OF p. p. 2
IN THE MATTER OF The Public Utilities Act, R.S.N.S 1989, c. 380, as amended and the The Maritime Link Act, S.N.S 2012 c.9 and the Maritime Link Cost Recovery Process Regulations, N.S. Reg. 189/2012

AI summary This regulatory proceeding pertains to the Public Utilities Act, the Maritime Link Act, and the Maritime Link Cost Recovery Process Regulations, indicating a focus on regulatory frameworks and cost recovery processes related to energy infrastructure in Nova Scotia.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →