Topic/Matter Intersection

Topic:"Public Utilities Act Nova Scotia" in M13083

Matter: Nova Scotia Power Inc. - CI C0068718 – IT - DERMS Solution Project - $2,965,414
2 passages 2 documents

Public Utilities Act Nova Scotia across all matters →

N-2NSPI (NSEB) RIR 1 to 5 1 passage
Qualitative Assessment p. pp. 40-41
Qualitative Assessment Criteria Assessment Rationale Ideally, a DER BCA framework should align with benefits and costs principles, Description methodologies and approaches consistent with established practice, like the National Standard Pr...

AI summary The document discusses the need for a Benefit-Cost Analysis (BCA) framework for Distributed Energy Resources (DER) in Nova Scotia, emphasizing alignment with established practices and considerations from other jurisdictions. It notes that DSM investments are evaluated using a Board-mandated BCA (PAC test) under the Public Utilities Act, while other investments follow the NSEB-approved Capital Expenditure Justification Criteria (CEJC). A recent BCA matter highlighted a debate on balancing cost-effectiveness with sustainable development goals.

103660NSEB (NSPI) IR 1 to 5 1 passage
NOVA SCOTIA ENERGY BOARD
NOVA SCOTIA ENERGY BOARD IN THE MATTER OF: THE PUBLIC UTILITIES ACT - and - IN THE MATTER OF: AN APPLICATION by NOVA SCOTIA POWER INCORPORATED to approve CI C0068718 – IT - DERMS Solution Project - $2,965,414

AI summary Nova Scotia Power Inc. has applied to the Nova Scotia Energy Board under the Public Utilities Act for approval of a $2,965,414 project related to the IT - DERMS Solution.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →