Matter: CI# 34622 - P-128.10 - NSPI WO - Upgrade L-8002 - $2,222,639
2 passages 1 document

Rate Base across all matters →

N-1Redacted Work Order 9/2/2010 2 passages
p. p. 1
An Emera Company · UARB APPRO VAL SHEET Project Title: · Jpgrade L-8002 CI Number: 34622 Capital Project Authorization Head Office Use: ATO Project Number: Final Cost • Date: August 30, 2010 · Location: Division: VEAD Expenditure Profi 8 c...

AI summary This document outlines the 'Upgrade L-8002' project by an Emera Company, including budget estimates, project estimates, and timelines. The project was submitted by Nova Scotia Power Inc. and approved by the Nova Scotia Utility and Review Board on August 30, 2010.

The following is a breakdown of costs associated with the Upgrade L-8002 p. p. 1
The following is a breakdown of costs associated with the Upgrade L-8002 • Administrative Overheads and Interest $313,376 27 provisioning, (iv) joint NSPl/affiliate provisioning, and (v) 28 such other arrangements as may be reasonably avai...

AI summary The text discusses the costs associated with Upgrade L-8002, including administrative overheads and interest, and outlines the terms of a contract between NSPI and EUS for the supply of contractor linework services. The contract was awarded in 2007 and extends from 2008 to 2010, with terms related to work hours, rates, and activities.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →