1011952025 Q4 Capital Reports
5 passages
As of December 31, 2025 This report includes all projects that have been removed from rate base per the conditions as established and approved in the CEJC and Accounting Policy 1520 - Rate Base, and their associated 2025 Income Statement i...
AI summary This report outlines capital items with unapproved plant in service above the $1,000,000 threshold, as established by the Board. It includes amendments related to the 'Forgone Earning Potential' column and the approval threshold change effective October 30, 2019.
(2) Capital Spend above $1,000,000 ($250,000 prior to October 30, 2019) associated with a preliminary engineering project that has been inactive (i.e. no internal or external engineering or scoping work, exceeding $10,000, being carried ou...
AI summary The document outlines capital spend details for a hydro plant project, including unapproved depreciation and interest expenses, and potential impacts on the 2025 income statement. The project, titled 'WRC LEM Penstock Intake,' has a threshold of $1,000,000 and a balance of $206,698, with a potential 2025 impact of $5,891.
Unapproved Spending Over $1M As of December 31, 2025 This report includes all capital projects greater than $1 million that are within the rate base thresholds as established and approved in the CEJC and Accounting Policy 1520 - Rate Base,...
AI summary This report details unapproved capital projects over $1M as of December 31, 2025, that are within rate base thresholds established by the CEJC and Accounting Policy 1520. It was included in compliance with a letter from the NSEB dated August 30, 2017 (M07568).
Note 2: This report has been amended to reflect the new Board approval threshold of $1,000,000, effective October 30, 2019. T
AI summary This note indicates that the report has been updated to reflect a new Board approval threshold of $1,000,000, effective October 30, 2019.
This report includes all capital projects greater than $1 million that are within the rate base thresholds as established and approved in the CEJC and Accounting Policy 1520 - Rate Base, that have not been approved by the Board at December...
AI summary This report lists capital projects over $1 million within approved rate base thresholds, excluding those approved by the Board by December 31, 2025. It differs from the Unapproved Spending report, which includes projects removed from the Rate Base. The report was included in compliance with a letter from the NSEB dated August 30, 2017 (M07568).