d inflation rate. The 2% inflation rate was sourced from NSP's IRP, while the 6.65% WACC was taken from NSP's 2024 WACC and AFUDC Rates for 2025 Application (Matter No. 11990, approved 31 May 2025). 66 A third category of NSP-built generat...
AI summary The text outlines the methodology for analyzing various cost categories for Nova Scotia's electricity system between 2026 and 2050. It specifies the use of a 2% inflation rate and a 6.65% WACC from NSP's 2024 application. Key categories discussed include Transmission CapEx (annualized over asset life), Production costs (variable costs like fuel, excluding capital), and Carbon emissions value (calculated based on carbon tax, policy exemptions, and the federal carbon price). It also notes that certain NSP-built generation CapEx is excluded due to its stable nature during the IESO transition.