N-3Incident Report - Redacted
5 passages
Update: Systems required for Evaluation are expected to be available by the end of 2025, with the required data for Year 4 (2024/25) Evaluation work to be Year 4 (2024/25) Evaluation available early in Q1 2026. Evaluation activities are ex...
AI summary The document outlines the timeline for the completion of the Year 4 (2024/25) Evaluation Report, expected to be filed in Q2 2026, and mentions the need for system restoration to support Time Varying Pricing (TVP) rates, including AMI meter communications and My Energy Insights.
formance in terms of advanced features and expected to be restored by the performance in order to administer TVP Rates. end of Q3 2026. October 1: "NS Power provides an annual report regarding its Time-of-Use Real Time Pricing (TOU RTP) ta...
AI summary NS Power is unable to prepare its 2025 Time-of-Use Real Time Pricing (TOU RTP) report to the NSEB due to data unavailability from May 2025 onward and missing files. The report is expected to be completed in Q2 2026 and is not expected to affect customers.
investigating the recovery of the relevant files. This is not expected to have an impact on customers." December 1: "Since NS Power’s last monthly update, NS Power has re-established the connection between Hitachi’s Portfolio Optimizer (Po...
AI summary NS Power has re-established connections between Hitachi’s Portfolio Optimizer software and its network, as well as the Plant Information data system, to restore dependent processes. These systems are essential for evaluating the ELIADC and determining the cost to serve PHP and One-Part RTP, with completion expected by January 31, 2026.
any relied on estimated bills. with all meters expected to be reconnected by the end of Notwithstanding these impacts, NS Power has implemented manual meter reading, limiting the number of estimated bills. The following metrics were not Ma...
AI summary NS Power has implemented manual meter reading to limit estimated bills, with all meters expected to be reconnected by the end of March 2026. Key metrics such as SAIDI, SAIFI, and outage reports remain unaffected.
eing billed appropriately? There is no standardized methodology for determining the impact on single-phase demand billing customers from the inability of demand registers to reset remotely. NS Power is reviewing all individual bills of the...
AI summary NS Power is reviewing the billing of 1,454 customers affected by a cyber-incident that caused the loss of remote demand reset functionality. Credits have been issued to 35 customers totaling $10,497, and 1,056 customers may face increased demand charges. Single-phase meters serve over 550,000 service locations.
99535NSPI Monthly Update Report #2
2 passages
Ongoing Regulatory Matters As a result of the impacts noted above, several matters before the Board have been affected, including: • rates-related, Page 4 of 16 October 1, 2025 C. Henwood • customer billing, • capital and ACE Plan, • finan...
AI summary The Incident has impacted multiple regulatory matters before the Board, including rates, billing, capital/ACE Plan, financial reporting, fuel adjustment mechanisms, reliability standards, and demand-side management. The Board is being updated on evolving impacts to ensure transparency.
As the Board has now requested, the identified impacts as understood to date are included in the sections that follow. Rates-Related Matters Rates-related matters have been affected by the Incident. Time Varying Pricing As noted by the NSEB...
AI summary The Incident has impacted rates-related matters, including Time Varying Pricing (TVP), Time-of-Use Real Time Pricing (TOU RTP) tariffs, and the Extra Large Industrial Active Demand Control (ELIADC) Tariff. NS Power faces data unavailability challenges for 2025 reports, though customer impact is not anticipated. NS Power will submit a proposed TVP approach and investigate missing data for ELIADC reporting.
100840NSPI Monthly Update Report #5
5 passages
Activities Updated Jan 31, 2026 Rates-Related Matters
AI summary The document lists 'Rates-Related Matters' updated on January 31, 2026, indicating ongoing regulatory proceedings focused on rate-related issues in Nova Scotia's energy sector.
Year 4 (2024/25) Evaluation Report Update: Systems required for the Evaluation are available. The Year 4 (2024/25) Evaluation work is underway and is expected to be completed in Q2 2026 with the Evaluation expected to be completed and file...
AI summary The Year 4 (2024/25) Evaluation Report on Time Varying Pricing (TVP) outlines progress toward restoring systems like AMI meters and My Energy Insights. The evaluation, expected to complete in Q2 2026, depends on full system restoration by year-end to reinstate TVP rates, as directed by the Board in M12499.
expected to be restored by the end of Q3 2026. RTP report will be completed in Q2 Time of Use - Real Time Pricing Tariffs Introduced NA NA NA NA 2026
AI summary The document outlines timelines for restoring services by Q3 2026 and completing an RTP (Real Time Pricing) report by Q2 2026. It mentions the introduction of Time of Use - Real Time Pricing Tariffs in 2026, indicating a focus on rate design and tariff implementation.
2026 Data processing and PortOps Extra Large Industrial Active Demand Work continues to populate the databases associated with the PortOps software to allow for the evaluation of the ELIADC and for determining cost to serve PHP and One-Par...
AI summary The document outlines ongoing efforts to populate PortOps software databases for evaluating the ELIADC tariff and modeling cost-to-serve PHP and One-Part RTP tariffs for 2025. Preliminary modeling for RTP integrity verification is underway, with completion expected by February 28, 2026.
, 2026 Activities Updated Jan 31, 2026 Rates-RelatedStandards Performance Matters The Company is on track to reconnect customer meters with the billing systems beginning in Performance Standards Introduced NA NA NA NA December 2025, with a...
AI summary The document outlines updates to rates-related performance standards and interconnection processes. Key activities include reconnecting customer meters to billing systems starting December 2025, completing by March 2026, and introducing an Affiliate Code of Conduct in Q1 2026.